Figure A-11
Column in a row of cabinets (A ≥ 70 mm)
Seal both sides of the column using sealing plates. Directions of the concave sides of the sealing
plates are shown in
Install cable trays over the cabinets on both sides of the blank cabinet place. If the cable trays cannot
be installed in combined mode, install them in layered mode, the upper for routing weak-current
cables while the lower for routing strong-current cables.
Install flat or rotating skylights over the aisle containment.
If sealing plates cannot be installed on both sides of the column, install sealing plates only near the
aisle containment.