5.9
Pick-up
5.9.1
Set operating height
Loaded material and ground condition determine the operating height of the pick-up.
Set the operating height of the pick-up at the same level by means
of the two guide wheels. The spring-loaded tines must not scratch
the ground. The distance between the spring-loaded tines and the
ground should be approx. 10-20 mm.
The operating height of the pick-up is set by means of the two-hole
perforated struts (2):
•
Front borehole = Lowest operating height of pick-up
•
Rear borehole = Highest operating height of pick-up
1.
Lift the pick-up (1).
2.
Secure tractor and machine against
accidental starting and rolling.
3.
Remove the rear linch pin of the perforated
strut (2).
4.
Use one hand to hold up the supporting
tube (3) of the guide wheel (4), while using
your other hand to hang the perforated
strut of the pick-up into the desired
borehole.
Fig. 55
Check the setting of the additional guide wheels in any case.
Summary of Contents for Giga-Vitesse CFS 3602
Page 2: ......
Page 4: ...Bad Laer den 26 03 2018 Dipl Kfm W Strautmann Managing Director...
Page 306: ...Circuit diagrams Giga Vitesse CFS 3602 4402 Giga Vitesse CFS 3602 DO 4402 DO 03 18 306 Fig 174...
Page 309: ...Circuit diagrams 309 Giga Vitesse CFS 3602 4402 Giga Vitesse CFS 3602 DO 4402 DO 03 18...
Page 310: ...Circuit diagrams Giga Vitesse CFS 3602 4402 Giga Vitesse CFS 3602 DO 4402 DO 03 18 310...
Page 313: ...Circuit diagrams 313 Giga Vitesse CFS 3602 4402 Giga Vitesse CFS 3602 DO 4402 DO 03 18...
Page 314: ...Circuit diagrams Giga Vitesse CFS 3602 4402 Giga Vitesse CFS 3602 DO 4402 DO 03 18 314...
Page 317: ...Circuit diagrams 317 Giga Vitesse CFS 3602 4402 Giga Vitesse CFS 3602 DO 4402 DO 03 18...
Page 318: ...Circuit diagrams Giga Vitesse CFS 3602 4402 Giga Vitesse CFS 3602 DO 4402 DO 03 18 318...
Page 320: ...Circuit diagrams Giga Vitesse CFS 3602 4402 Giga Vitesse CFS 3602 DO 4402 DO 03 18 320...
Page 326: ......