10.1.
iSWAY-FC
®
The iSWAY-FC
®
, to the installation site is optionally supplied on a special BIG FOOT support
system.
Unloading from the means of transport and transporting the aeration unit to the place of assembly
should be done by means of a pallet truck and it is recommended to lift the unit from the side of
the service switch as shown in figure 10.1 because the weight distribution of the unit is not
symmetrical and the centre of gravity is not in the geometric centre of the unit, therefore special
care should be taken when transporting the iSWAY-FC
®
.
According to fig. 10.2. lifting by means of a crane is depicted, one set (4 pcs.) of transport screws
with an extended M16 threaded eye is supplied on request. Screws for transport should be made
of material with minimum strength parameters: Re=235[MPa], Rm=380 [MPa] e.g. C15. Remove
the plugs from the holes and screw in the eye bolts as far as the stop. Remove the transportation
screws after the required adjustment of the unit, and secure the holes with previously removed
plugs.
In the case of supplies on pallets individual elements - sections of the aeration unit to the assembly
site, these elements are to be assembled on site by the SMAY service. This documentation does
not include manuals and guidelines for assembling the iSWAY-FC
®
. Immediately after the device
has been delivered to the installation site, check the condition of the packaging and the complete
documentation.
After assembling the aeration unit blocks or with the iSWAY
®
aeration unit delivered as a whole,
only transport them in their normal operating position.
Fig. 10.1. Transportation by means of a pallet truck.