16.
Preparation for commissioning
Commissioning of the iSWAY-FC, iSWAY-WFC, iSWAY-RFC (SAFETY WAY system), must
only be carried out by the SMAY Service or an authorised SMAY Service Centre when the fire
protection system is put into operation.
Before starting up the unit/system, perform the steps to prepare the unit/system for start-up. To
do this, check that:
1.
there is no contamination inside the ducts and the aeration unit
2.
during the assembly work, the components of the aeration unit and installation,
automation or automation elements were not damaged,
3.
all components of the unit/system are properly installed mechanically and connected to
the ventilation network,
4.
the earthing conductors connecting the aeration unit to the ventilation ducts are correctly
installed,
5.
electricity receivers are properly wired and ready for operation,
6.
the automation elements in the entire aeration unit are correctly mounted, wired and
connected.
16.1.
Electrical installation
Before closing the components of the SAFETY WAY system, check them:
1.
based on the electrical and automation design for a given object (system) the compatibility
of wire connections and connections between terminals,
2.
the correctness of the applied protections of all electricity consumers,
3.
tightening of all screws and correct installation of the holding elements and electrical
connections (also unused auxiliary terminals - if any, unused glands, etc.),
4.
cables and conductors in terms of meeting all the requirements for protection, layout,
cross sectioning, etc,
5.
correct execution of grounding and protective connections,
6.
the inside of electrical and automation equipment, whether there are any residual wires
left in it,
7.
condition of gaskets and sealing surfaces
After performing the above mentioned checking activities, all inspection panels should be carefully
closed.
NOTE!!!
Operation with open inspection panels is not permitted.
16.2.
Checking the readiness of the device for operation
The check of the overall efficiency and readiness for operation of the device comes down to
checking the correctness of the power supply and the correctness of the individual components