Step 5.
Install a new front I/O assembly. See “Installing the front I/O assembly” on page 121.
Installing the front I/O assembly
The front I/O assembly contains an operator information panel and two cables. If you have removed the front
I/O assembly, install a new one before turning on the server.
To install the front I/O assembly, do the following:
Step 1.
Carefully push the front I/O assembly into the server as shown until the front I/O assembly clicks
into place.
Figure 54. Front I/O assembly installation
Step 2.
Reconnect the USB cable and the operator information panel cable to the connectors on the
system board. Make sure the relevant cables pass through the cable clips.
Step 3.
Complete the parts replacement. See “Completing the parts replacement” on page 172.
Removing the operating temperature enhancement kit
To remove the operating temperature enhancement kit, do the following:
Step 1.
Turn off the server. Then, disconnect all external cables and remove all peripheral devices.
Step 2.
Remove the server cover. See “Removing the server cover” on page 88.
Step 3.
Remove the PCI riser-card assembly. See “Removing the PCI riser-card assembly” on page 93.
Step 4.
Disconnect the operating temperature enhancement kit connector from the system board.
Removing and installing server components
121
Summary of Contents for x3250 m6
Page 1: ...Lenovo System x3250 M6 Installation and Service Guide Machine Types 3633 and 3943 ...
Page 6: ...iv Lenovo System x3250 M6 Installation and Service Guide ...
Page 18: ...4 Lenovo System x3250 M6 Installation and Service Guide ...
Page 60: ...46 Lenovo System x3250 M6 Installation and Service Guide ...
Page 100: ...86 Lenovo System x3250 M6 Installation and Service Guide ...
Page 516: ...502 Lenovo System x3250 M6 Installation and Service Guide ...
Page 678: ...664 Lenovo System x3250 M6 Installation and Service Guide ...
Page 685: ...Taiwan Class A compliance statement Appendix E Notices 671 ...
Page 695: ......
Page 696: ......