Operation
226
Pos: 89.9 /Überschriften/Überschriften 2/A-E/BBindeei nrichtung @ 20\mod_1239003005331_78.docx @ 225610 @ 2 @ 1
18.2
Tying unit
Pos: 89.10 /BA/Ei nstellungen/Groß packenpresse/Bindegarn ei nfädel n/Bi ndegar n einl egen @ 275\mod_1404376981999_78.docx @ 2066534 @ 3 @ 1
18.2.1
Setting the tying twine in place
The process of setting the tying twine in place is identical for the left and right side of the baler.
The procedure described below for setting the tying twines in place therefore applies to both
side of the baler.
The machine must be stopped while the twine is prepared and inserted:
• Shut down and safeguard the machine, see chapter Safety -> Safety routines, "Shutting
down and safeguarding the machine".
• Secure the knotter shaft by moving the safety lever (1).
Pos: 89.11 /BA/Ei nstellungen/Groß packenpresse/Bindegarn ei nfädel n/Knoterwelle sicher n H S Baurei he @ 71\mod_1305873545803_78.docx @ 641641 @ @ 1
Secure knotter shaft
1
2
2
a
b
BPHS0059
b
a
1
Fig. 144
Each time before you set new tying twine in place, the knotter shaft must be secured so that the
needle yoke cannot be put in motion.
To do this:
• To do this, move the safety lever (1) from position (a) to position (b) and set it down on the
journal (2)
Pos: 89.12 /BA/Ei nstellungen/Groß packenpresse/Bindegarn ei nfädel n/Hinweis Abstellen des Bi ndegar ns i n die Garnkästen @ 20\mod_1239008751331_78.docx @ 226534 @ @ 1
Note
When placing the tying twine in the twine box, make certain that the labeling on the rolls can be
read. Make certain the side marked "Up" is facing up.
Pos: 89.13 /BA/Ei nstellungen/Groß packenpresse/Bindegarn ei nfädel n/Hinweis Endl osballen g epr esst @ 92\mod_1326728080272_78.docx @ 781560 @ @ 1
Note
The safety lever (2) must be in position (a) for the baling process! Otherwise an endless bale
will be formed when the knotter shaft is secured.
Pos: 89.14 /Layout Module /---------------Seitenumbr uch---------------- @ 0\mod_1196175311226_0.docx @ 4165 @ @ 1