Installation and commissioning
Commissioning
5.9
Commissioning
CAUTION
In addition to the work given here, checks on the drive system may be
necessary as set out in the requirements and regulations of the drive / system
manufacturer. This also contains the proper attachment of protective covers.
This work must be performed by the person responsible for the machine.
Before commissioning of the i
MAPLA
system
for the first time, carry out
the following checks. Remove any defects before commissioning. Before
commissioning, read and follow the safety instructions in the General
chapter.
Ö
General safety instructions, page 58.
>
Make sure the performance data of the connected lifting magnet match
the data of your
i
MAPLA system.
>
Make sure the generator is mounted correctly and firmly.
Ö
MAPLA 8, 13, 17 and 20, page 69
Ö
Ö
Make sure that the protection covers of the generator drive and the
drive itself are mounted correctly.
>
Make sure that the MMI is mounted correctly and in the driver's field of
view.
Ö
>
Make sure that all connecting cables are correct and are installed correctly
and protected against the mechanical requirements.
Ö
Installation of cables, page 64.
>
Make sure that all connector plugs are plugged in correctly.
>
Make sure that the connecting cables between MMI and the control
button are properly connected to the control button unit (joystick).
>
Make sure that the total machine meets the requirements of all the
applicable directives.
>
Start the system.
Ö
Establish the system’s readiness for use, page 106.
>
Check the correct function of the system by comparing it with the
description.
>
Acknowledge the first start-up in the commissioning report.
Ö