5-36
C60 Breaker Protection System
GE Multilin
5.2 PRODUCT SETUP
5 SETTINGS
5
When a 0 value is involved in a change, the changes to the
MODBUS TCP PORT NUMBER
setting take effect when the
C60 is restarted.
Do not set more than one protocol to the same TCP/UDP port number, as this results in unreliable operation of
those protocols.
i) PROTOCOL
The Protocol menu setting allows selection of one of the following protocols: DNP 3.0, IEC60870-104, or IEC60870-103.
For any change to take effect, restart the unit.
The table shows which of DNP 3.0, IEC 60870-5-104, IEC 60870-5-103, and IEC 61850 protocols are operational on the
RS232, RS485, and Ethernet ports. It shows all possible combinations of the
PROTOCOL
and
DNP CHANNEL 1(2) PORT
set-
tings.
Table 5–6: PORT AND PROTOCOL COMBINATIONS
PROTOCOL
SETTING
DNP CHANNEL 1(2) PORT
SETTINGS
RS232
RS485
ETHERNET
DNP
Channel 1: Eth TCP
Channel 2: Eth TCP
Modbus
Modbus
DNP, Modbus, IEC 61850
Channel 1: Eth TCP
Channel 2: none
Modbus
Modbus
DNP, Modbus, IEC 61850
Channel 1: none
Channel 2: Eth TCP
Modbus
Modbus
DNP, Modbus, IEC 61850
Channel 1: Eth UDP
Channel 2: none
Modbus
Modbus
DNP, Modbus, IEC 61850
Channel 1: Eth TCP
Channel 2: RS485
Modbus
DNP
DNP, Modbus, IEC 61850
Channel 1: Eth TCP
Channel 2: RS232
DNP
Modbus
DNP, Modbus, IEC 61850
Channel 1: Eth UDP
Channel 2: RS485
Modbus
DNP
DNP, Modbus, IEC 61850
Channel 1: Eth UDP
Channel 2: RS232
DNP
Modbus
DNP, Modbus, IEC 61850
Channel 1: RS485
Channel 2: Eth TCP
Modbus
DNP
DNP, Modbus, IEC 61850
Channel 1: RS232
Channel 2: Eth TCP
DNP
Modbus
DNP, Modbus, IEC 61850
Channel 1: RS485
Channel 2: RS232
DNP
DNP
Modbus, IEC 61850
Channel 1: RS232
Channel 2: RS485
DNP
DNP
Modbus, IEC 61850
Channel 1: RS485
Channel 2: none
Modbus
DNP
Modbus, IEC 61850
IEC 104
Modbus
Modbus
IEC 104, Modbus, IEC 61850
IEC 103
Modbus
IEC 103
Modbus, IEC 61850
NOTE
Summary of Contents for C60
Page 10: ...x C60 Breaker Protection System GE Multilin TABLE OF CONTENTS ...
Page 30: ...1 20 C60 Breaker Protection System GE Multilin 1 5 USING THE RELAY 1 GETTING STARTED 1 ...
Page 420: ...5 284 C60 Breaker Protection System GE Multilin 5 10 TESTING 5 SETTINGS 5 ...
Page 466: ...8 4 C60 Breaker Protection System GE Multilin 8 1 FAULT LOCATOR 8 THEORY OF OPERATION 8 ...
Page 478: ...9 12 C60 Breaker Protection System GE Multilin 9 6 DISPOSAL 9 MAINTENANCE 9 ...
Page 492: ...A 14 C60 Breaker Protection System GE Multilin A 1 PARAMETER LISTS APPENDIX A A ...
Page 648: ...E 10 C60 Breaker Protection System GE Multilin E 1 OVERVIEW APPENDIX E E ...
Page 660: ...F 12 C60 Breaker Protection System GE Multilin F 2 DNP POINT LISTS APPENDIX F F ...
Page 670: ...H 8 C60 Breaker Protection System GE Multilin H 2 ABBREVIATIONS APPENDIX H H Z Impedance Zone ...
Page 672: ...H 10 C60 Breaker Protection System GE Multilin H 3 WARRANTY APPENDIX H H ...
Page 682: ...x C60 Breaker Protection System GE Multilin INDEX ...