Platform Safety-aerial EEC-0070
V1.3
Platform Safety
Wind, weather, and unstable conditions.
Any potentially hazardous conditions.
F.
Aerial device shall be operated with outriggers and stabilizers fully deployed and
properly set.
G.
The operator shall verify that the aerial device is set up and maintained within one
percent of level (0.56°) during a personnel lift.
H.
For aerial devices with a boom-attached platform, verify that the platform is attached
as outlined in the installation section.
I.
Not allow the platform’s rating to be exceeded when loads are transferred to the
elevated platform.
J.
Not knowingly allow the platform load to exceed the platform rating.
K.
Travelling with personnel in the equipment’s personnel platform.
L.
The operator shall perform all movements if the platform in a slow, controlled
manner to minimize sudden and unexpected movements of the platform.
M.
Set all brakes and locks on the aerial device after positioning of the personnel
platform and before any personnel platform work.
N.
Move the platform under controlled conditions.
O.
The operator shall not move the platform over, under, or in the vicinity of power lines
or electrical hazards unless the requirements of the minimum clearance table are
met.
P.
Not lift any loads on a boom winch load line with personnel in the platform.
Q.
Not disable, or allowed to be disabled, any aerial device safety device.
GROUND CREW
A.
Visually inspect the platform prior to each lift to verify all attachments and the
platform structure are secure.
B.
Inspect and attach the platform to the aerial device as specified by the manufacturer.
C.
Verify the platform is evenly loaded, material secured, and the total platform weight
does not exceed the platform rating or the reduced aerial device lift capacity.
Summary of Contents for E190
Page 2: ......
Page 64: ...Hirschmann J1939 Install EEC 0110 V1 0 Hirschmann J1939 Network Installation...
Page 72: ...Hirschmann J1939 Install EEC 0110 V1 0 Hirschmann J1939 Network Installation...
Page 75: ...Hirschmann J1939 Install EEC 0110 V1 0 Hirschmann J1939 Network Installation...
Page 140: ......
Page 141: ......
Page 146: ...TITLE...
Page 147: ...TITLE...
Page 149: ...TITLE...
Page 150: ...TITLE...
Page 151: ...TITLE...
Page 152: ...TITLE...
Page 153: ......
Page 154: ......
Page 155: ......
Page 156: ......
Page 157: ...TITLE...
Page 158: ...TITLE...
Page 159: ...TITLE...
Page 160: ...TITLE...
Page 161: ...TITLE...
Page 162: ...TITLE...
Page 173: ...Bolt Torque EEC 0016 V1 2 Bolt Torque...
Page 179: ...Four Section Boom Operation aerial EEC 0081 V1 3 Four Section Boom Operation...
Page 199: ...Five Section Boom Operation aerial EEC 0080 V1 3 Five Section Boom Operation...
Page 227: ......
Page 230: ...1 INFORMAZIONI GENERALI GENERAL INFORMATION...
Page 248: ...8 ACCESSORI PER ARGANI DA SOLLEVAMENTO E TRAINO LIFTING AND RECOVERY WINCH ACCESSORIES...
Page 265: ...11 TABELLE DI CONVERSIONE CONVERSION TABLES...
Page 268: ...12 CONDIZIONI GENERALI DI VENDITA CONDITIONS OF SALE...
Page 279: ...4 5200S...
Page 280: ...5 6000S...
Page 333: ......
Page 334: ......
Page 357: ...Appendix B Parts Index ELLIOTT Built for You E190 Manual B 1...