Section 4 — CFC Commissioning
Part No. 750-263
4-23
To set combustion:
1. Check inlet gas pressure and reset low gas pressure switch.
2. At Operation screen set firing rate to low fire. Review burner
sequence before proceeding.
3. Turn LOCAL/REMOTE switch to LOCAL.
4. Initiate burner firing sequence. The burner switch is accessed
via the CB Falcon Operation page (
Figure 4-9
). If the burner
does not ignite, adjust choke counterclockwise slightly until you
can see a slight yellow flame at the burner during ignition.
Clockwise adjustments to the low-fire offset screw may also be
tried. Check that gas pressure to gas valve inlet is sufficient to
fire burner (see Table 4-3 for gas pressure requirements).
5. After burner lights, maintain in low fire position. At low fire,
using main choke on gas valve and a combustion analyzer set
O2 level within 3-8% O2.
6. Manually modulate the burner to high fire. Adjust the gas choke
if necessary to obtain desired O2% (6% - 7%).
7. Modulate to low fire and fine tune offset screw to obtain desired
O2% (6% - 7%).
Verify adjustments by modulating back and forth between low and
high fire.
While setting combustion observe gas pressure at low fire and at
high fire. Ensure pressure is within limits shown in Table 4-3.
8. High Air Pressure Switch settings
The High Air Pressure witch (HAPS) is used to safely shut down the
boiler in case of a blocked flue or blocked condensate condition.
The HAPS switch setting for each model CFC can be found below:
Table 4-3 HAPS Settings
The HAPS has a manual reset, similar to the High/Low gas pressure
switches.
Note:
In the event of a HAPS lockout, investigate possible causes
before attempting to restart boiler.
9. Limit Controls Check
The Modulation Off (operating limit) and High Limit functions can
be tested while the boiler is operating by adjusting the respective
Figure 4-9 Operation screen
Model
Setting
CFC-500
3.5” W.C.
CFC-750
3.5” W.C.
CFC-1000
3.5” W.C.
CFC-1500
4.5” W.C.
CFC-1800
4.5” W.C.
CFC-2500
5.25” W.C.
Summary of Contents for CFC-1000
Page 35: ...Section 2 Installation Part No 750 263 2 21 Figure 2 23 Gas Piping ...
Page 47: ...Section 2 Installation Part No 750 263 2 33 Figure 2 41 Electrical Connection Diagram ...
Page 49: ...Section 2 Installation Part No 750 263 2 35 Figure 2 43 CFC Wiring Diagram dual fuel units ...
Page 50: ...Section 2 Installation 2 36 Part No 750 263 ...
Page 70: ...Section 3 Stack and Intake Vent Sizing and Installation 3 20 Part No 750 263 ...
Page 102: ...Section 4 CFC Commissioning 4 32 Part No 750 263 ...
Page 108: ...Section 5 Service and Maintenance 5 6 Part No 750 263 ...
Page 113: ...Section 6 Parts Part No 750 263 6 5 Figure 6 3 Casing Table 6 5 Casing parts ...
Page 117: ...Section 6 Parts Part No 750 263 6 9 Figure 6 7 Electrical assemblies single fuel ...
Page 123: ...APPENDIX A CB FALCON CONTROLLER ...
Page 124: ......
Page 244: ...CB FALCON 750 265 120 ...
Page 245: ...APPENDIX B CB FALCON PLUG IN MODULE ...
Page 246: ......
Page 250: ......
Page 251: ...APPENDIX C GAS VALVE ...
Page 252: ......
Page 269: ...APPENDIX D CB FALCON MODBUS COMMUNICATION ...
Page 270: ......