Benchmark with Edge [I]: Operation-Maintenance Manual
SECTION 7
– BOILER SEQUENCING TECHNOLOGY
OMM-0145_A99
• GF-218 • 9/18/2019 Technical Support • (800) 526-0288 • Mon-Fri, 8 am - 5 pm EST Page
116
of
157
7.3.5
Option 5 Remote Setpoint: Direct Wired Header Temp Sensor & 4-20ma
Setpoint Drive
OPTION 5
Instructions: Remote Setpoint, Direct Wired Header Temp Sensor, 4-20ma Setpoint
Drive
NOTE:
Both
Header Temp Sensor
and
4-20ma Direct Drive
must be wired. See the
Edge [i]
Controller Manual
(OMM-0141, GF-213-B) for more information.
Step 1: HEADER TEMP SENSOR WIRING
– BST MANAGER Unit
1. On the
BST
Manager
unit, connect the
Header Temp Sensor
to the
Feed Forward
(FFWD)
terminals on the P-1 Harness via the terminal block labeled
Header Temp sensor
on the I/O Board.
2. Ground the shield to any
SHLD
terminal on the I/O Board.
NOTES:
•
The
Header Temp Sensor
must be installed between 2 and 10 feet (0.61 and 3.1m)
downstream of the
last
boiler in the plant’s supply water header.
•
Shielded pair 18 - 22 AWG cable is recommended for
Header Temp Sensor
wiring.
There is no polarity to be observed. The ground for the shield is at the
SHLD
terminal
on the I/O Board. The sensor end of the shield must be left free and ungrounded.
Step 2: DIRECT WIRED 0-20mA or 4-20mA WIRING
– BST MANAGER Unit
1. Connect the
4-20mA
or
0-20mA
terminals from the Direct Drive source to the
Ain+
and
Ain-
terminals on the BST Manager
’s I/O Board.
2. Connect the shield to any
SHLD
terminal on the I/O Board.
NOTES:
•
Shielded pair 18 - 22 AWG cable is recommended for this connection. Polarity must be
observed.
•
The ground for the shield is at the driver signal source.
Continued on next page
HEADER TEMP SENSOR
I/O BOARD
I/O BOARD
HEADER TEMP SENSOR