Installation - Electrical
Installation Checklist
Complete this checklist as the unit is installed, to verify that all recommended
procedures are accomplished before the unit is started. This checklist does
not replace the detailed instructions given in the Sections 2 and 3 of this
manual. Read both sections completely, to become familiar with the instal-
lation procedures, prior to beginning the work.
Receiving
•
Verify that the unit nameplate data corresponds to the ordering informa-
tion.
•
Inspect the unit for shipping damage and any shortages of materials.
Report any damage or shortage to the carrier.
Unit Location and Mounting
•
Inspect the location desired for installation and verify adequate service
access clearances.
•
Provide drainage for evaporator and condenser water, if applicable.
•
Remove and discard all shipping materials (cartons, etc.)
•
Install optional neoprene or spring isolators, if required.
•
Level the unit and secure it to the mounting surface.
Unit Water Piping
•
Flush all unit water piping before making final connections to the unit.
•
Connect the water piping to the evaporator and condenser, if applicable.
•
Install pressure gauges and shutoff valves on the water inlet and outlet to
the evaporator, if applicable.
•
Install a water strainer in the entering chilled water line.
•
Install a balancing valve and flow switch (discretionary) in the leaving
chilled water line, if applicable.
•
Install a drain with shutoff valve or a drain plug on the evaporator, if appli-
cable.
•
Vent the chilled water and condenser water system at high points in the
system piping, ifapplicable.
Unit Refrigerant Piping (RTUA and RTCA)
NOTE:
Do not release refrigerant to the atmosphere!
•
Perform initial leak test.
•
Braze properly sized and constructed liquid line to liquid line connections
on the unit.
•
Braze properly sized and constructed hot gas (discharge) lines at hot gas
line connections on the unit.
•
Leak test the unit and all refrigerant piping connections.
•
Connect the unit power supply wiring with fused disconnect to the termi-
nal block (or unit-mounted disconnect) in the power section of the control
panel.
•
Connect the control power supply wiring with fused-disconnect to the
Summary of Contents for R Series
Page 17: ...RLC SVX07A EN 17 Installation Mechanical Figure 2 Rigging and Lifting for RTWA Units ...
Page 22: ...22 RLC SVX07A EN Installation Mechanical Figure 7 Rigging and Lifting for RTUA Units ...
Page 25: ...RLC SVX07A EN 25 Installation Mechanical Figure 10 Rigging and Lifting for RTCA Condenser ...
Page 69: ...RLC SVX07A EN 69 Installation Electrical Figure 28 Interconnecting Wiring from RTUA to RTCA ...
Page 129: ...RLC SVX07A EN 129 Start Up Procedures Figure 41 RTWA Unit Sequence of Operation ...
Page 130: ...130 RLC SVX07A EN Start Up Procedures Figure 42 RTUA Unit Sequence of Operation ...
Page 154: ...154 RLC SVX07A EN Diagnostics ...
Page 156: ...156 RLC SVX07A EN 3332 ...
Page 158: ...158 RLC SVX07A EN 3333 ...
Page 160: ...160 RLC SVX07A EN 3334 ...
Page 162: ...162 RLC SVX07A EN 3335 ...
Page 164: ...164 RLC SVX07A EN 3336 ...
Page 166: ...166 RLC SVX07A EN 5119 ...
Page 168: ...168 RLC SVX07A EN 5143 ...
Page 170: ...170 RLC SVX07A EN 5144 ...
Page 172: ...172 RLC SVX07A EN 5145 ...
Page 174: ...174 RLC SVX07A EN 5146 ...
Page 176: ...176 RLC SVX07A EN 6008 ...
Page 178: ...178 RLC SVX07A EN 6009 ...
Page 180: ...180 RLC SVX07A EN 5147 ...
Page 182: ...182 RLC SVX07A EN 6526 ...
Page 184: ...184 RLC SVX07A EN 5150 ...
Page 186: ...186 RLC SVX07A EN 6010 ...