RLC-SVX07A-EN
131
Unit Shutdown Procedures
Temporary Shutdown and Restart
To shut the unit down for a short time, use the following procedure:
1.
Press the Stop key on the Clear Language Display. The compressors will
continue to operate and, after unloading for 20 seconds, will stop when
the compressor contactors de-energize.
2.
Stop the water circulation by turning off both the chilled water pump and
condenser pump.
To restart the unit after a temporary shutdown, restart the chilled water pump
and press the AUTO key. The unit will start normally, provided the following
conditions exist:
1.
The UCM must receive a call for cooling and the differential to-start must
be above the setpoint.
2.
All system operating interlocks and safety circuits must be satisfied.
Extended Shutdown Procedure
The following procedure is to be followed if the system is to be taken out of
service for an extended period of time, eg., seasonal shutdown:
1.
Test the unit for refrigerant leakage and repair as necessary.
2.
Open the electrical disconnect switches for the chilled water pump. Lock
the switch in the “OPEN” position.
CAUTION
Pump Damage!
Lock the chilled water pump and condenser water pump
disconnects open, to prevent pump damage.
3.
Close all chilled water supply valves. Drain the chilled water from the
evaporator and condenser.
4.
Open the unit main electrical disconnect and unit mounted disconnect (if
installed) and lock on the “OPEN” position. If optional control power
transformer is not installed, open and lock the 115 V disconnect.
CAUTION
Accidental Start-up!
Lock the disconnects on the “OPEN” position to prevent
accidental start-up and damage to the system when it has been
setup for extended shutdown.
5.
At least every three months (quarterly), check the pressure in the unit to
verify that the refrigerant charge is intact.
System Restart after Extended Shutdown
Follow the procedures below to restart the unit after extended shutdown:
1.
Verify that the liquid line service valves, oil line, compressor discharge
service valves and suction service valves are open (backseated).
Summary of Contents for R Series
Page 17: ...RLC SVX07A EN 17 Installation Mechanical Figure 2 Rigging and Lifting for RTWA Units ...
Page 22: ...22 RLC SVX07A EN Installation Mechanical Figure 7 Rigging and Lifting for RTUA Units ...
Page 25: ...RLC SVX07A EN 25 Installation Mechanical Figure 10 Rigging and Lifting for RTCA Condenser ...
Page 69: ...RLC SVX07A EN 69 Installation Electrical Figure 28 Interconnecting Wiring from RTUA to RTCA ...
Page 129: ...RLC SVX07A EN 129 Start Up Procedures Figure 41 RTWA Unit Sequence of Operation ...
Page 130: ...130 RLC SVX07A EN Start Up Procedures Figure 42 RTUA Unit Sequence of Operation ...
Page 154: ...154 RLC SVX07A EN Diagnostics ...
Page 156: ...156 RLC SVX07A EN 3332 ...
Page 158: ...158 RLC SVX07A EN 3333 ...
Page 160: ...160 RLC SVX07A EN 3334 ...
Page 162: ...162 RLC SVX07A EN 3335 ...
Page 164: ...164 RLC SVX07A EN 3336 ...
Page 166: ...166 RLC SVX07A EN 5119 ...
Page 168: ...168 RLC SVX07A EN 5143 ...
Page 170: ...170 RLC SVX07A EN 5144 ...
Page 172: ...172 RLC SVX07A EN 5145 ...
Page 174: ...174 RLC SVX07A EN 5146 ...
Page 176: ...176 RLC SVX07A EN 6008 ...
Page 178: ...178 RLC SVX07A EN 6009 ...
Page 180: ...180 RLC SVX07A EN 5147 ...
Page 182: ...182 RLC SVX07A EN 6526 ...
Page 184: ...184 RLC SVX07A EN 5150 ...
Page 186: ...186 RLC SVX07A EN 6010 ...