RLC-SVX07A-EN
27
Installation - Mechanical
Unit Isolation and Leveling
Mounting
Construct an isolated concrete pad for the unit or provide concrete footings at
each of the four unit mounting points. Mount the unit directly to the concrete
pads or footings.
Level the unit using the base rail as a reference. The unit must be level within
1/4” over the entire length. Use shims as necessary to level the unit.
Isolators
The RTWA, RTUA and RTAC units should use neoprene isolators. Install
isolators at each unit mounting point.
Neoprene Isolator Installation.
Install the optional neoprene isolators at each mounting location. Isolators are
identified by part number and color.
1.
Secure the isolators to the mounting surface, using the mounting slots in
the isolator base plate, as shown in
Figure
12
,
13
and
14
. Do not fully
tighten the isolator mounting bolts at this time.
2.
Align the mounting holes in the base of the unit, with the threaded
positioning pins on the top of the isolators.
NOTE:
RTWA/RTUA mount front isolators on cross rails not long rails for
best performance.
3.
Lower the unit on to the isolators and secure the isolator to the unit with
a nut. Maximum isolator deflection should be approximately 1/4”.
4.
Level the unit carefully. Refer to “Leveling”. Fully tighten the isolator
mounting bolts.
Summary of Contents for R Series
Page 17: ...RLC SVX07A EN 17 Installation Mechanical Figure 2 Rigging and Lifting for RTWA Units ...
Page 22: ...22 RLC SVX07A EN Installation Mechanical Figure 7 Rigging and Lifting for RTUA Units ...
Page 25: ...RLC SVX07A EN 25 Installation Mechanical Figure 10 Rigging and Lifting for RTCA Condenser ...
Page 69: ...RLC SVX07A EN 69 Installation Electrical Figure 28 Interconnecting Wiring from RTUA to RTCA ...
Page 129: ...RLC SVX07A EN 129 Start Up Procedures Figure 41 RTWA Unit Sequence of Operation ...
Page 130: ...130 RLC SVX07A EN Start Up Procedures Figure 42 RTUA Unit Sequence of Operation ...
Page 154: ...154 RLC SVX07A EN Diagnostics ...
Page 156: ...156 RLC SVX07A EN 3332 ...
Page 158: ...158 RLC SVX07A EN 3333 ...
Page 160: ...160 RLC SVX07A EN 3334 ...
Page 162: ...162 RLC SVX07A EN 3335 ...
Page 164: ...164 RLC SVX07A EN 3336 ...
Page 166: ...166 RLC SVX07A EN 5119 ...
Page 168: ...168 RLC SVX07A EN 5143 ...
Page 170: ...170 RLC SVX07A EN 5144 ...
Page 172: ...172 RLC SVX07A EN 5145 ...
Page 174: ...174 RLC SVX07A EN 5146 ...
Page 176: ...176 RLC SVX07A EN 6008 ...
Page 178: ...178 RLC SVX07A EN 6009 ...
Page 180: ...180 RLC SVX07A EN 5147 ...
Page 182: ...182 RLC SVX07A EN 6526 ...
Page 184: ...184 RLC SVX07A EN 5150 ...
Page 186: ...186 RLC SVX07A EN 6010 ...