64
RLC-SVX07A-EN
Installation - Electrical
Also, provide a set of auxiliary contacts for condenser water pump starter
5K27 to interlock cooling tower fan starter (5K28) operation (if used) with the
condenser water pump starter. This insures that the cooling tower fan runs
only when the condenser water pump is operating.
Alarm/Running/Maximum Capacity Outputs
Terminals 1 to 7 on terminal strip TB4 of the 1U1 board provide a variety of
contact outputs on the RTWA and RTUA units. These are dependent upon
the setting of Programmable Relay Setup (Service Setting Menu) and its
relationship to diagnostics, compressors operating and the system operating
at full capacity.
As shown in
Figure
19
, there are three relays. Relays 1 has SPDT contacts.
Relays 2 and 3 have SPST normally-open contacts. The relays provide three
output configurations, as shown in
Figure
19
, and each configuration offers
four choices as to how each relay is to respond to a set of diagnostics.
Table
27
shows the twelve settings available in Programmable Relay Setup
(Service Setting Menu) and the diagnostics which are issued for each set of
conditions.
Alarm/Running/Maximum Capacity Indicator Wiring
If the optional remote Alarm/Running/Maximum Capacity contacts are used,
provide electrical power, 115 VAC (contact load not to exceed 1150 VA inrush,
115 VA sealed), with fused-disconnect to a customer furnished remote
device. Also provide proper remote device ground connection.
Figure 27
Typical RTWA Chiller Interlock
Summary of Contents for R Series
Page 17: ...RLC SVX07A EN 17 Installation Mechanical Figure 2 Rigging and Lifting for RTWA Units ...
Page 22: ...22 RLC SVX07A EN Installation Mechanical Figure 7 Rigging and Lifting for RTUA Units ...
Page 25: ...RLC SVX07A EN 25 Installation Mechanical Figure 10 Rigging and Lifting for RTCA Condenser ...
Page 69: ...RLC SVX07A EN 69 Installation Electrical Figure 28 Interconnecting Wiring from RTUA to RTCA ...
Page 129: ...RLC SVX07A EN 129 Start Up Procedures Figure 41 RTWA Unit Sequence of Operation ...
Page 130: ...130 RLC SVX07A EN Start Up Procedures Figure 42 RTUA Unit Sequence of Operation ...
Page 154: ...154 RLC SVX07A EN Diagnostics ...
Page 156: ...156 RLC SVX07A EN 3332 ...
Page 158: ...158 RLC SVX07A EN 3333 ...
Page 160: ...160 RLC SVX07A EN 3334 ...
Page 162: ...162 RLC SVX07A EN 3335 ...
Page 164: ...164 RLC SVX07A EN 3336 ...
Page 166: ...166 RLC SVX07A EN 5119 ...
Page 168: ...168 RLC SVX07A EN 5143 ...
Page 170: ...170 RLC SVX07A EN 5144 ...
Page 172: ...172 RLC SVX07A EN 5145 ...
Page 174: ...174 RLC SVX07A EN 5146 ...
Page 176: ...176 RLC SVX07A EN 6008 ...
Page 178: ...178 RLC SVX07A EN 6009 ...
Page 180: ...180 RLC SVX07A EN 5147 ...
Page 182: ...182 RLC SVX07A EN 6526 ...
Page 184: ...184 RLC SVX07A EN 5150 ...
Page 186: ...186 RLC SVX07A EN 6010 ...