Laying the Connecting Cables
●
To lay the cables between the BC and EC2, remove the lower grills in the two rear covers.
●
To lay the connection cables between stacked cabinets, you can cut out the pre-stamped
recesses in the bottom of EC1 and the top of the BC with a pair of diagonal cutting pliers
and break them out with a pair of flat-nosed pliers.
Figure 4-57
HiPath 3750 - Installing a Three-Cabinet System (Stacked)
7
Caution
Be careful when breaking out the recesses. Remove any sharp edges and corners.
BC
EC1
Inside
the cabinet
Washers
EC2
BC