Maintenance
135
Figure 5-22. Locating pin
CAUTION
Do not touch the glass portion of the lamp. Touching the lamp could damage it. If the
lamp is dirty, clean it using lint-free toweling moistened with ethanol.
6.
Install the lamp screws.
7.
Install the lead wires and fasten the knobs.
8.
Replace the access panel.
9.
Return the analyzer to the READY mode, if necessary.
10.
Wait 40 minutes for the lamp to stabilize.
NOTE:
You can perform the daily shutdown 2 while you are waiting.
11.
Then, check the lamp energy.
12.
Register the data and verify that attenuations register at 100%, voltages are between
5–9, and scatter is no greater than ±40.
13.
Perform the cell blank measurement test.
NOTE:
Siemens recommends the assays on the system be calibrated after the lamp is
replaced.
14.
Run QC controls to verify that all assays are within the laboratory’s established
control ranges.
Washing the ISE electrodes lines
Materials required:
• Dummy electrode with o-ring and cap
(REF 05938765, PN 073-0342-01)
• ISE detergent solution
(REF 01307361, B01-4174-01)
Time: 25 minutes
Analyzer mode: Manual operation
BIOHAZARD
Wear personal protective
equipment.
Use universal precautions.
Summary of Contents for ADVIA 2400
Page 1: ...ADVIA 2400 Chemistry System Operator s Guide 073D0403 01 Rev A 2009 06 ...
Page 12: ...12 ADVIA 2400 Operator s Guide ...
Page 64: ...64 ADVIA 2400 Operator s Guide ...
Page 98: ...98 ADVIA 2400 Operator s Guide ...
Page 165: ...Maintenance 165 ...
Page 167: ...Troubleshooting 167 ...
Page 173: ...System Setup 173 ...
Page 177: ...System Setup 177 ...
Page 181: ...Appendix 181 ...
Page 182: ...182 ADVIA 2400 Operator s Guide ...