96
Sheeter SVC 525C
Set-up, commissioning
Commissioning
7.4
Commissioning
• After the stationary mains connection, the machine must be commis-
sioned.
• Separate installation and commissioning instructions are required for
this.
7.5
Final check of the protective devices
After commissioning the machine, be absolutely certain to carry out a final
check of the protective devices.
Procedure:
Check that all covers and protective devices are installed and fully func-
tional.
For this purpose, use the checklist for the protective devices.
See chapter “4.5 Checkliste Sicherheits- und Schutzeinrichtungen”.
7.6
Inspection after initial operation
Proceed as follows to conduct the inspection after initial operation.
Prerequisites
These prerequisites must be fulfilled:
• The machine is ready for operation.
Carrying out an in-
spection
Here's how to carry out an inspection:
Check all tapes and belts to make sure they run centered and have the
necessary tension.
If required, readjust these.
See Maintenance chapter.
The inspection has been carried out.
Only have the machine commissioned by MBO Service or by a customer
service technician authorized by MBO.
20 operating hours after initial operation, it is necessary to perform an
inspection of all belts and tapes.
Summary of Contents for SVC 525C
Page 1: ...Sheeter Translation of the original operating manual Keep for future reference SVC525C ...
Page 48: ...44 Sheeter SVC 525C Product description Technical data ...
Page 66: ...62 Sheeter SVC 525C Structure and function Protective devices ...
Page 90: ...86 Sheeter SVC 525C Transport interim storage Interim storage of the machine ...