CHAPTER 7 - PROGRAMMING INFORMATION AND SUGGESTIONS
152
7.1.6.1 Loads with Constant
Torque (P202=3 and
P120=1 point)
1) Set P121 as percent of the nominal motor torque, necessary for
the motor + load during running;
2) Set P102 to the time required for the motor start. At first set short
times: 10s to 15s;
3) With the torque control you can start the load smoothly within short
starting times due to the linearity of the start speed ramp.
Figure 7.11
- Start with constant torque control, 1 point
7.1.6.2 Loads with Higher Initial
Torque (P202=3 and
P120=3 points)
1) Through this function you can achieve a smooth and linear starting
ramp. This function is very useful for conveyors belt;
2) Through the load curve you can set a starting torque 10% to 20%
higher than the load torque for each one of the points P121, P123,
P122 and the times at P102 and P124;
3) For the first start you can use a speed measuring instrument, thus
ensuring the desired acceleration or the desired speed curve;
4) If no load curves are available, you can apply a similar method
as the current ramp method. Also the torque limit, P120=1, can
be used for executing the first starts and afterwards changing to
this function.
Figure 7.12
- Starting with quadratic torque control, 3 points,
with higher initial load
Tn(%)
Start
Speed
P102
0
Enable
Disable
t(s)
Maximum Time
P121
Tn Nominal
Load Torque
Torque Control
P120 =1
P102
Torque
Control
P401
P400
P104 =0
P121
P640
P406
P404
P402
P405
Tn(%)
Start
Speed
P124
0
Enable
Disable
t(s)
Maximum Time
P121
Tn Nominal
Load Torque
Torque Control
P123
P102
P122
P120 =3
P102
Torque
Control
P401
P400
P122
P121
P640
P406
P404
P402
P405
P123
P124
P104 =0