Initial Powering Operations for the Edge-SS Line
2-17
KVAL Operation/Service Manual
Description of the Six Light Panel
The six lights on this panel indicate the status of the power-up of the system. Each machine has
this panel.
The Sequence the lights activate is as follows:
Sequence Order
Light Designation
Description
1
Control Power
This
light illuminates when the Control Transformer turned on
and the power is working on secondary side-of transformer
2
Overload Relay
Checks the Overload Relay in the E-Box. In some cases, this
circuit is jumped. In these cases it should always light when
the Control Power turns on.
3
E-Stop
All gates are closed and the E-stops are not activated when
this light is on.
4
Stop
This light will be on if Machine Stop button is deactivated.
5
Start
This light will be on once the Machine Start button is pressed
and the ACR Relay is latched.
6
24VDC
This
light comes on once the ACR is latch and the 24VDC
power Supply is working
Control Power
First
Overload Relay
Second
E-Stop
Third
24VDC –
Sixth
Stop –
Fourth
Start –
Fifth
Summary of Contents for Edge-SS
Page 5: ...KVAL Edge SS Operation Service Manual ...
Page 12: ...KVAL Edge SS Line Operation Service Manual ...
Page 32: ...Safety Sign Off Sheet 1 20 KVAL Operation Service Manual ...
Page 35: ...Definitions 2 45 KVAL Operation Service Manual ...
Page 91: ...Definitions KVAL Operation Service Manual 2 56 ...
Page 109: ...System IT Administration 4 4 KVAL Operation Service Manual ...
Page 142: ...Collet Torque Values 5 33 KVAL Operation Service Manual ...
Page 143: ...Troubleshooting Electrical Problems 6 30 KVAL Operation Service Manual ...
Page 173: ......
Page 177: ......
Page 178: ......
Page 179: ......