Initial Powering Operations for the Edge-SS Line
KVAL Operation/Service Manual
2-16
Initial Powering Operations for the Edge-SS Line
This section describes how to power up and to power down the Edge-SS Line.
Powering up the system includes:
• Applying power to the entire system
• Starting the Control Circuit
Powering down the system includes:
• Shutting down the control power
• Removing power from the entire system
How to Power Up the Edge-SS Line
1.
Ensure factory air is applied to each machine and main air supply is turned on.
2.
Check that all E-Stop buttons are out and safety gates are closed.
Note:
A pop-up is displayed on the user screen if an E-Stop is pressed. The pop-up
will indicate which E-Stop has been activated
3.
Make sure the electrical disconnect each electrical
cabinet is turned to the ON position.
4.
Switch the green
CONTROL TRANSFORMER
switches to the ON
positions. They should light up.
5.
Push the green
START MACHINE
buttons to “boot up” the
machines.
Note:
Boot up may take 2 to 3 minutes.
6.
All lights on the status light panels on the electrical
box should be illuminated.
See “Description of the
Six Light Panel” on page 2-17
Note:
If a status light does not turn on during the power
up process, see
the trouble shooting chapter in the
Service Manual.
.
Summary of Contents for Edge-SS
Page 5: ...KVAL Edge SS Operation Service Manual ...
Page 12: ...KVAL Edge SS Line Operation Service Manual ...
Page 32: ...Safety Sign Off Sheet 1 20 KVAL Operation Service Manual ...
Page 35: ...Definitions 2 45 KVAL Operation Service Manual ...
Page 91: ...Definitions KVAL Operation Service Manual 2 56 ...
Page 109: ...System IT Administration 4 4 KVAL Operation Service Manual ...
Page 142: ...Collet Torque Values 5 33 KVAL Operation Service Manual ...
Page 143: ...Troubleshooting Electrical Problems 6 30 KVAL Operation Service Manual ...
Page 173: ......
Page 177: ......
Page 178: ......
Page 179: ......