Installation
XHD Installation, Operation, and Maintenance Manual
24
NOTICE:
Remove all dirt from the mounting pads in order to ensure that the correct leveling is
achieved. Failure to do so can result in equipment damage or decreased performance.
a) Put one machinist's level lengthwise on one of the two pads.
b) Put the other level across the center of the two pads.
c) Level the pads by adjusting the four jackscrews in the corners.
Make sure that the machinist's level readings are as close to zero as possible, both
lengthwise and across.
Item Description
1.
Driver's mounting pads
2.
Machinist's levels
3.
Foundation bolts
4.
Jackscrews
5.
Grout hole
6.
Pump's mounting pads
Figure 15: Level pump mounting pads
6. Hand-tighten the nuts for the foundation bolts.
7. Check that the driver's mounting pads are level and adjust the jackscrews and the
foundation bolts if necessary.
The correct level measurement is a maximum of 0.167 mm/m | 0.002 in./ft .
Summary of Contents for Goulds Pumps XHD
Page 1: ...Installation Operation and Maintenance Manual XHD ...
Page 2: ......
Page 151: ...Parts Listings and Cross Sectionals XHD Installation Operation and Maintenance Manual 149 ...
Page 153: ...Certification CE or CE ATEX XHD Installation Operation and Maintenance Manual 151 ...
Page 156: ...Certification CE or CE ATEX XHD Installation Operation and Maintenance Manual 154 ...