Installation
XHD Installation, Operation, and Maintenance Manual
23
d) Make sure that the center jackscrews do not touch the foundation surface yet.
Item Description
1.
Jackscrew
2.
Baseplate
3.
Foundation
4.
Plate
Figure 13: Jackscrews
3. Level the driver mounting pads:
NOTICE:
Remove all dirt from the mounting pads in order to ensure that the correct leveling is
achieved. Failure to do so can result in equipment damage or decreased performance.
a) Put one machinist's level lengthwise on one of the two pads.
b) Put the other machinist's level across the ends of the two pads.
c) Level the pads by adjusting the four jackscrews in the corners.
Make sure that the machinist's level readings are as close to zero as possible, both
lengthwise and across.
Use the baseplate-leveling worksheet when you take the readings.
Item Description
1.
Machinist's levels
2.
Driver's mounting pads
3.
Foundation bolts
4.
Jackscrews
5.
Grout hole
6.
Pump's mounting pads
Figure 14: Level driver mounting pads
4. Turn the center jackscrews down so that they rest on their plates on the foundation surface.
5. Level the pump mounting pads:
Summary of Contents for Goulds Pumps XHD
Page 1: ...Installation Operation and Maintenance Manual XHD ...
Page 2: ......
Page 151: ...Parts Listings and Cross Sectionals XHD Installation Operation and Maintenance Manual 149 ...
Page 153: ...Certification CE or CE ATEX XHD Installation Operation and Maintenance Manual 151 ...
Page 156: ...Certification CE or CE ATEX XHD Installation Operation and Maintenance Manual 154 ...