SN
Item
Description
3
Upper-layer
device
Ensure that the upper-layer device meets the following
requirements:
l
The position of the interconnection port of the upper-layer
device is correct.
l
The upper-layer device works in the normal state and can be
used for the commissioning.
4
Board
(daughter
board)
The board (daughter board) selected should meet the
requirements for the external ports.
NOTE
l
Different boards (daughter boards) provide different external ports.
For details about the boards and their external ports on the MA5600T/
MA5603T/MA5608T, see Board Overview of the MA5600T/
MA5603T/MA5608T Hardware Description.
l
During the system startup, you are not allowed to install or remove
any boards.
1.2.2 Preparing Software
This topic describes how to prepare the software required before the commissioning. This
facilitates the subsequent commissioning.
shows the software checklist before the commissioning.
Table 1-2
Software checklist
SN
Item
Description
1
Software
package
Ensure that files in the software package for the commissioning
are complete and the software version is correct.
2
Software
commissioning
tools
Ensure that all the commissioning tools are available. The
common commissioning tools are as follows:
l
HyperTerminal (provided by the Windows OS): used for
logging in to the MA5600T/MA5603T/MA5608T through
the CLI.
l
TFTP, SFTP, and FTP tools: used for loading software.
They can be downloaded from
. You are advised to use SFTP tools.
l
Client software key generator Puttygen.exe, client software
key convertor sshkey.exe and SSH client software
putty.exe: used for logging in to the MA5600T/MA5603T/
MA5608T through the SSH.
SmartAX MA5600T/MA5603T/MA5608T Multi-service
Access Module
Commissioning and Configuration Guide
1 Commissioning
Issue 01 (2014-04-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
4