Monitoring
Parameter
Displayed on
the Host
Device Port
Application in the F01S300 Cabinet
Environment
Tem
VTEM2
Environment temperature sensor
Smoke
SMOKE
Smoke sensor (optional configuration)
Water
WATER
Water sensor (optional configuration)
Procedure
Step 1
Log in to the device through the maintenance terminal and add an ETP4830 (SMU).
Run the
emu add
command to add the SMU.
Step 2
Check the default configurations of the power system.
Run the
interface emu
command to enter environment monitoring mode and then run the
display power system parameter
and
display power environment parameter
commands to
query the default configurations.
Step 3
Configure parameters required for lead-acid batteries.
Run the
power battery parameter
command to configure parameters required for batteries,
including the management parameters, charging parameters, power-off parameters, and high-
temperature power-off parameters. You can use default values of these parameters for
configuration.
Step 4
Run the
power battery temperature
command to configure the upper/lower temperature test
limits, temperature compensation coefficient, and the upper/lower alarm temperature limits of
the battery set.
Step 5
(Optional) Configure discharging testing parameters.
l
Run the
power battery-test
command to configure the discharging testing parameters,
including the automatic power-off test, scheduled automatic test, test interval for automatic
discharging, test time for delayed discharging, voltage at the stop of the test, number of
batteries in a battery set, time limit for the discharging test, time limit for simplified
discharging test, alarm thresholds for discharging efficiencies. You can use default values
of these parameters for configuration.
l
Run the
display power battery-test info
command to query the discharge testing
information about the batteries.
Step 6
Run the
power off
command to configure the load power-off and battery set power-off voltage
parameters
Step 7
Run the
power temperature-off
command to configure the battery high-temperature power-off
parameters.
Step 8
Configure the environment monitoring parameters of the SMU system.
Run the
power environment
command to configure the upper alarm threshold and the upper
and lower test thresholds for the temperatures and humidity. After these parameters are set, the
SmartAX MA5600T/MA5603T/MA5608T Multi-service
Access Module
Commissioning and Configuration Guide
1 Commissioning
Issue 01 (2014-04-30)