After the hardware installation, a stand-alone MA5600T/MA5603T/MA5608T should be
commissioned to ensure that the stand-alone MA5600T/MA5603T/MA5608T works in the
normal state.
The MA5600T/MA5603T/MA5608T provides multiple interfaces for interconnection. This
topic describes the interconnection commissioning of the MA5600T/MA5603T/MA5608T.
Maintenance and Management Commissioning
To ensure the stability of the MA5600T/MA5603T/MA5608T, you need to verify the
maintainability and reliability of the device after completing the stand-alone commissioning and
interconnection commissioning.
1.2 Commissioning Preparations
This topic describes the hardware, software, and tool preparations for the commissioning.
1.2.1 Checking Hardware
This topic describes how to prepare the hardware required before the commissioning. This
facilitates the subsequent commissioning.
Context
lists the hardware to be checked before the commissioning.
Table 1-1
Hardware checklist
SN
Item
Description
1
Power supply
and grounding
Ensure that the power cable and the grounding meet the following
requirements:
l
The power cable and the ground cable are connected properly
and are in good contact.
l
The labels of the power cable, ground cable, and power
distribution switch are correct, legible and complete.
l
The connectors of the external ground cables and protection
ground cables of the cabinet are connected properly, without
any damage.
l
The power supply for the device is in the normal state.
2
Cables and
connectors
Check the local maintenance serial port cable, network cable,
optical fiber, subscriber cable, and connectors, and ensure that
they meet the following requirements:
l
The connectors are tight and firm.
l
The cable jacket is intact.
l
Cable labels are legible.
l
Cables are bundled properly.
SmartAX MA5600T/MA5603T/MA5608T Multi-service
Access Module
Commissioning and Configuration Guide
1 Commissioning
Issue 01 (2014-04-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3