4. Field drill 3/8" holes (47) in the sidewall using the bottom hole in each starter brackets (32 and 35)
as guides. Install 5/16" x 1" flange bolts (1) and 5/16" flange nuts (10) to the bottom holes. Tighten
all the hardware to the recommended torque specifications. See
Bolt Torque Specifications, page
5. Working down from the starter brackets (32 and 35) and in vertical alignment, install a ladder
standoff bracket (33) at every horizontal seam or 32" from the previously installed bracket. Install a
5/16" x 1" flange bolt (1) and 5/16" flange nut (10), securing each ladder standoff bracket (33) to the
sidewall.
NOTE:
Installing a plumb line to the starter brackets (32 and 35) will help keep each bracket aligned
vertically.
6. Install a ladder reinforcing strap (34) to the ladder standoff brackets (33) using 5/16" x 1" flange bolts
(1) and 5/16" flange nuts (10).
NOTE:
For optimal reinforcement, install the ladder reinforcing straps (34) in a diagonal fashion as
shown.
7. Tighten all the hardware to the recommended torque specifications. See
.
8. Install the ladder (46) to the starter brackets (32 and 35) using 5/16" x 1" flange bolts (1) and
5/16" flange nuts (10), but do not tighten at this time.
9. Install a 5/16" x 1" carriage bolt (4) to a standoff wedge (36) and insert the standoff wedge (36) into
the outside of the ladder (46) channel.
10.Connect the standoff wedge (36) to the standoff bracket (33) by installing a 5/16" flange nut (10),
but do not tighten, allowing for adjustment.
PNEG-5490D-2X
90' Diameter EVO-50 Beam 2X Bin
207
Summary of Contents for EVO-50
Page 6: ...NOTES 6 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 34: ...NOTES 34 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 130: ...NOTES 130 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 188: ...NOTES 188 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 220: ...NOTES 220 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...