Installing the Intermediate Purlins
Intermediate purlins must be installed to connect each A-frame assembly together. The intermediate
purlins connecting each A-frame assembly have six holes on each side to secure them with the purlin
clips.
Before You Begin
All A-frame assemblies must be installed and secured to both the center collar and the eave brackets.
1. Position the intermediate purlin (132) between the purlin clips (60 and 62) located outside of each
A-frame assembly (133).
2. Install six 1/2" x 1-3/4" flange bolts (5) and 1/2" flange nuts (17) to each end of the purlin (132),
securing the intermediate purlin (132) to the purlin clips (60 and 62).
3. Tighten all the hardware to the recommended torque specifications. See
Figure 8-28
Installing the intermediate purlin
5
1/2" x 1-3/4" flange bolt (S-10252)
62
Right purlin clip (CTR-0950)
17
1/2" flange nut (S-10253)
132
Purlin
60
Left purlin clip (CTR-0876)
133
A-frame assembly
NOTE:
Purlin part numbers and hardware count to secure the purlin clips will vary with location.
After You Finish
Repeat this process to install the remaining intermediate purlins between the A-frame assemblies.
168
PNEG-5490D-2X
90' Diameter EVO-50 Beam 2X Bin
Summary of Contents for EVO-50
Page 6: ...NOTES 6 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 34: ...NOTES 34 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 130: ...NOTES 130 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 188: ...NOTES 188 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 220: ...NOTES 220 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...