Preparation for the Roof Exhauster Installation
Using the roof exhauster mounting plate, some preparations are required for the roof panels to which the
roof exhauster mounting plate will be installed.
Before You Begin
Determine the location of the roof exhauster and set aside the roof panels that the roof exhauster
mounting plate will span.
What You Should Know
This procedure is to cut the exhauster airflow hole. Use the roof exhauster mounting plate as a template
to determine the correct location for field cutting the roof exhauster hole.
1. Position the roof panels (77) spanned by the roof exhauster mounting plate (75) on the ground.
Align the roof panel holes as if they are installed on the bin.
2. Temporarily install the roof exhauster mounting plate (75) to the roof panels (77) using 5/16" x 1"
flange bolts (1) and 5/16" flange nuts (10). Make sure all the holes are aligned and the teeth of the
roof exhauster mounting plate (75) are nestled in between two roof ribs. Also field drill all required
holes on the roof panels (77).
3. Using the roof exhauster mounting plate (75), mark or scribe the hole (78) to be cut.
Tip
If tabs are already bent, flip the mounting plate (75) upside down to scribe the hole location.
Figure 9-6
Temporary installation of exhauster mounting plate for marking
1
5/16" x 1" flange bolt with sealing
washer (S-10260)
77
Roof panel
10
5/16" flange nut (S-3611)
78
Marked or scribed hole to be cut
70
Holes to be field drilled
79
Field bent inside tab on roof exhauster mounting plate
75
Exhauster mounting plate
(CTR-1302)
PNEG-5490D-2X
90' Diameter EVO-50 Beam 2X Bin
197
Summary of Contents for EVO-50
Page 6: ...NOTES 6 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 34: ...NOTES 34 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 130: ...NOTES 130 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 188: ...NOTES 188 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 220: ...NOTES 220 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...