4. Install 5/16" x 1" flange bolts (2) and 5/16" flange nuts (19), leaving the end hole open for the next
eave angle to be installed.
NOTE:
The quantity of flange bolts (2) and flange nuts (19) may vary, depending on the sidewall
punch pattern.
5. Bend the eave angle tabs (127) upward to conform with each roof panel rib.
6. Install the optional tab seal (28) to the tabs of the eave angle (25) as shown from the inside of the
bin.
7. Tighten all the hardware to the recommended torque specification. See
.
Figure 8-4
Installing the eave angle to the sidewall
2
5/16" x 1" flange bolt with sealing washer (S-10260)
26
Second eave angle (CTR-0721)
19
5/16" flange nut (S-3611)
28
Optional tab seal (CRP-4802)
22
Top outside stiffener (CTS-4016XX)
126
Top sidewall sheet
25
First eave angle (CTR-0721)
127
Eave angle tab
After You Finish
Continue this process to install the remaining eave angles to the sidewall sheet.
PNEG-5490D-2X
90' Diameter EVO-50 Beam 2X Bin
135
Summary of Contents for EVO-50
Page 6: ...NOTES 6 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 34: ...NOTES 34 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 130: ...NOTES 130 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 188: ...NOTES 188 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 220: ...NOTES 220 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...