2. Align the holes on the first top panel (121) with the holes in the center collar channel brackets (120)
and the inner center collar flange (119).
3. Install 3/8" x 1" flange bolts (3) and 3/8" flange nuts (15) only to the holes at one end to secure the
first top panel (121) with the center collar channel bracket (120).
NOTE:
Leave the flange bolts (3) hand tight to remove it later when tucking the last top panel (121)
under the first top panel (121).
Figure 8-39
Installing the first top panel
3
3/8" x 1" flange bolt with sealing washer (S-7487)
120
Center collar channel bracket
(CTR-1580)
15
3/8" flange nut (S-9426)
121
Top panel (CTR-1585)
119
Inner center collar (CTR-1581-BS)
PNEG-5490D-2X
90' Diameter EVO-50 Beam 2X Bin
181
Summary of Contents for EVO-50
Page 6: ...NOTES 6 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 34: ...NOTES 34 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 130: ...NOTES 130 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 188: ...NOTES 188 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 220: ...NOTES 220 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...