Connecting the Tension Member to the Eave Bracket
Tension members are installed to the eave bracket around the inside of the bin.
Before You Begin
Make sure all the eave brackets and eave angles are installed.
What You Should Know
IMPORTANT:
Install bolts with bolt head on the backside of the eave bracket as shown.
1. Lift and support one tension member (29) against the inside mating surface and another tension
member (29) against the outside mating surface of the eave bracket (23).
2. Install 1/2" x 2-1/4" HHCS bolts (6) and 1/2" flange nuts (17) to each end of the tension members
(29).
3. Tighten all the hardware to the recommended torque specifications. See
Figure 8-5
Installing the tension member to the eave bracket
6
1/2" x 2-1/4" HHCS bolts (S-7894)
27
Eave angle (CTR-0721)
17
1/2" flange nut (S-10253)
29
Tension member (CTR-2190)
23
Eave bracket (CTR-2174-BS)
After You Finish
Repeat this process to install the remaining tension members to the eave bracket.
136
PNEG-5490D-2X
90' Diameter EVO-50 Beam 2X Bin
Summary of Contents for EVO-50
Page 6: ...NOTES 6 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 34: ...NOTES 34 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 130: ...NOTES 130 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 188: ...NOTES 188 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...
Page 220: ...NOTES 220 PNEG 5490D 2X 90 Diameter EVO 50 Beam 2X Bin ...