Inspect the Boom
Extend/Retract Cables
Genie specifications require that this procedure be
performed every 250 hours or quarterly, whichever
comes first.
The boom extend/retract cables are responsible for
the extension and retraction of the number 3 boom
tube. Inspecting for foreign objects, damage and/or
improper adjustment of the boom extend/retract
cables and related components on a regular basis
is essential to good machine performance and safe
machine operation. The boom extend and retract
functions should operate smoothly and be free of
hesitation, jerking and unusual noise.
1 Raise the boom to horizontal and fully extend
the boom.
2 After the boom is fully extended, lower the boom
until the platform is at chest height. Turn the
machine off.
3
S-60, S-65, S-60X, S-60XC, S-60 TRAX and
S-65 TRAX:
Remove the boom end cover
retaining fasteners and remove the cover.
S-60 HC:
Remove the boom end cover from the
pivot end of the boom while guiding the small
cable from the string potentiometer out of the
slot of the cover. Rest the cover and string
potentiometer on the counterweight.
Component damage hazard. The
cable from the string potentiometer
can become damaged if it is
kinked or pinched.
4 Remove the retaining fasteners from the access
covers located on the side of the boom at the
platform end of the machine. Remove the
covers.
5 Visually inspect the cables and components
through both inspection holes for the following:
• Frayed or broken wire strands
• Kinks in the cables
• Corrosion
• Paint or foreign materials on the cable
• Split or cracked cable ends
• Cables are on all pulleys
• Extend cable break limit switch arm is
centered in the pivot plate
• Cables have equal tension
• Cables at end of adjustment range
• No broken or damaged pulleys
• No unusual or excessive pulley wear
• All fasteners in place and secure
•
S-60 HC:
String potentiometer cable break
limit switch arm is securely attached to end
of cable
Note: A flashlight and inspection mirror may be
necessary to thoroughly inspect the above items.
Note: A pulley groove gauge should be used to
check the condition of the pulleys.
CHECKLIST
B
PROCEDURES
Summary of Contents for S-60 HC
Page 1: ......
Page 215: ...Section 6 Schematics December2013 6 7 Ford DSG 423 Engine Wire Harness 6 8 ...
Page 218: ...December2013 Section 6 Schematics 6 10 Ford MSG 425 Engine Wire Harness 6 9 ...
Page 219: ...Section 6 Schematics December2013 6 11 Electrical Schematic Options All Models 6 12 ...
Page 222: ...December2013 Section 6 Schematics 6 14 Wiring Diagram Belt Driven Generator 6 13 ...
Page 223: ...Section 6 Schematics December2013 6 15 Wiring Diagram 3kW Hydraulic Generator 6 16 ...
Page 234: ...December2013 Section 6 Schematics 6 26 Hydraulic Schematic 2WD Models after SN 21396 6 25 ...
Page 238: ...December2013 Section 6 Schematics 6 30 Hydraulic Schematic 4WD Models after SN 21396 6 29 ...
Page 365: ...Section 6 Schematics December2013 6 157 Electrical Schematic S 60 HC CE 6 158 ...
Page 368: ...December2013 Section 6 Schematics 6 160 Chassis Wiring Diagram S 60 HC CE 6 159 ...
Page 373: ...Section 6 Schematics December2013 6 165 Platform Control Box Wiring Diagram S 60 HC CE 6 166 ...
Page 461: ......