4 - 20
S-60 • S-65 • S-60 TRAX • S-65 TRAX
Part No. 147753
S-60 HC • S-60X • S-60XC
December 2013
Section 4 • Repair Procedures
4-1
Cable Track
The primary boom cable track guides the cables
and hoses running up the boom. It can be repaired
link by link without removing the cables and hoses
that run through it. Removing the entire primary
boom cable track is only necessary when
performing major repairs that involve removing the
primary boom.
How to Remove the Cable Track,
S-60, S-60X, S-60XC, S-60 HC
and S-60 TRAX
Note: When removing a hose assembly or fitting,
the O-ring (if equipped) on the fitting and/or the
hose end must be replaced. All connections must
be torqued to specification during installation. Refer
to Section 2,
Hydraulic Hose and Fitting Torque
Specifications
.
1 Raise the boom to a horizontal position.
2 Locate the cables from the boom cable track to
the platform control box. Number each cable
and its entry location at the platform control
box.
3 Disconnect the cables from the platform control
box.
4 Remove the electrical outlet box bracket
mounting fasteners. Remove the outlet box and
lay it to the side.
Boom Components
5 Remove the hose and cable clamp from the
platform support.
6 Tag, disconnect and plug the hydraulic hoses
from the counterbalance valve manifold located
on the platform rotator. Cap the fittings on the
manifold.
Bodily injury hazard. Spraying
hydraulic oil can penetrate and
burn skin. Loosen hydraulic
connections very slowly to allow
the oil pressure to dissipate
gradually. Do not allow oil to
squirt or spray.
7 Tag, disconnect and plug the platform leveling
slave cylinder hydraulic hoses from the
bulkhead fittings on the side of the primary
boom. Cap the bulkhead fittings.
Bodily injury hazard. Spraying
hydraulic oil can penetrate and
burn skin. Loosen hydraulic
connections very slowly to allow
the oil pressure to dissipate
gradually. Do not allow oil to
squirt or spray.
8 Locate all electrical cables under the boom at
the pivot end that enter the cable track.
9 Tag and disconnect the electrical connectors for
all cables that enter the cable track.
10 Remove the retaining fasteners from the
electrical connector receptacles for the cables
that enter the cable track.
Summary of Contents for S-60 HC
Page 1: ......
Page 215: ...Section 6 Schematics December2013 6 7 Ford DSG 423 Engine Wire Harness 6 8 ...
Page 218: ...December2013 Section 6 Schematics 6 10 Ford MSG 425 Engine Wire Harness 6 9 ...
Page 219: ...Section 6 Schematics December2013 6 11 Electrical Schematic Options All Models 6 12 ...
Page 222: ...December2013 Section 6 Schematics 6 14 Wiring Diagram Belt Driven Generator 6 13 ...
Page 223: ...Section 6 Schematics December2013 6 15 Wiring Diagram 3kW Hydraulic Generator 6 16 ...
Page 234: ...December2013 Section 6 Schematics 6 26 Hydraulic Schematic 2WD Models after SN 21396 6 25 ...
Page 238: ...December2013 Section 6 Schematics 6 30 Hydraulic Schematic 4WD Models after SN 21396 6 29 ...
Page 365: ...Section 6 Schematics December2013 6 157 Electrical Schematic S 60 HC CE 6 158 ...
Page 368: ...December2013 Section 6 Schematics 6 160 Chassis Wiring Diagram S 60 HC CE 6 159 ...
Page 373: ...Section 6 Schematics December2013 6 165 Platform Control Box Wiring Diagram S 60 HC CE 6 166 ...
Page 461: ......