Section 3 • Scheduled Maintenance Procedures
B-1
Inspect the Battery
Genie specifications require that this procedure be
performed every 250 hours or quarterly, whichever
comes first.
Proper battery condition is essential to good engine
performance and operational safety. Improper fluid
levels or damaged cables and connections can
result in engine component damage and hazardous
conditions.
Electrocution/burn hazard. Contact
with hot or live circuits could result
in death or serious injury. Remove
all rings, watches and other
jewelry.
Bodily injury hazard. Batteries
contain acid. Avoid spilling or
contacting battery acid. Neutralize
battery acid spills with baking soda
and water.
1 Put on protective clothing and eye wear.
2 Be sure that the battery cable connections are
free of corrosion.
Note: Adding terminal protectors and a corrosion
preventative sealant will help eliminate corrosion on
the battery terminals and cables.
3 Be sure that the battery hold downs and cable
connections are tight.
Checklist B Procedures
4 Be sure that the battery separator wire
connections are tight (if equipped).
5 Fully charge the battery(s) and allow the
battery(s) to rest at least 6 hours.
6 Remove the battery vent caps and check the
specific gravity of each battery cell with a
hydrometer. Note the results.
7 Check the ambient air temperature and adjust
the specific gravity reading for each cell as
follows:
•
Add 0.004 to the reading of each cell for
every 10° / 5.5° C above 80° F / 26.7° C.
•
Subtract 0.004 from the reading of each cell for
every 10° / 5.5° C below 80° F / 26.7° C.
Result: All battery cells display an adjusted
specific gravity of 1.277 or higher. The battery
is fully charged. Proceed to step 11.
Result: One or more battery cells display a
specific gravity of 1.217 or below. Proceed to
step 8.
8 Perform an equalizing charge OR fully charge
the battery(s) and allow the battery(s) to rest at
least 6 hours.
9 Remove the battery vent caps and check the
specific gravity of each battery cell with a
hydrometer. Note the results.
Summary of Contents for S-60 HC
Page 1: ......
Page 215: ...Section 6 Schematics December2013 6 7 Ford DSG 423 Engine Wire Harness 6 8 ...
Page 218: ...December2013 Section 6 Schematics 6 10 Ford MSG 425 Engine Wire Harness 6 9 ...
Page 219: ...Section 6 Schematics December2013 6 11 Electrical Schematic Options All Models 6 12 ...
Page 222: ...December2013 Section 6 Schematics 6 14 Wiring Diagram Belt Driven Generator 6 13 ...
Page 223: ...Section 6 Schematics December2013 6 15 Wiring Diagram 3kW Hydraulic Generator 6 16 ...
Page 234: ...December2013 Section 6 Schematics 6 26 Hydraulic Schematic 2WD Models after SN 21396 6 25 ...
Page 238: ...December2013 Section 6 Schematics 6 30 Hydraulic Schematic 4WD Models after SN 21396 6 29 ...
Page 365: ...Section 6 Schematics December2013 6 157 Electrical Schematic S 60 HC CE 6 158 ...
Page 368: ...December2013 Section 6 Schematics 6 160 Chassis Wiring Diagram S 60 HC CE 6 159 ...
Page 373: ...Section 6 Schematics December2013 6 165 Platform Control Box Wiring Diagram S 60 HC CE 6 166 ...
Page 461: ......