Monitor and control equipment
48
i-Vu CCN Pro 4.2
To create a group override CCN time schedule
When a group of controllers is assigned a matching
Override Group
number, an override from a single
controller in the group can cause all of the controllers in the Override group to be to overridden. The override
duration is set in i-Vu CCN Pro, even though i-Vu CCN Pro supports push-button override.
In order for a controller to initiate a remote override request:
•
Set the actual duration of the override in i-Vu CCN Pro.
•
Do not set the controller’s local override hours to
0.
•
The controller's setting must be greater-than or equal-to the i-Vu CCN Pro override duration.
NOTES
•
It is recommended that the local override value at the controller be set to its maximum possible setting.
•
Equipment activation, when using PBOR’s, is normally instantaneous, but varying delays are possible.
•
Do not press the button a second time, as this could cause the override to be cancelled.
In order to have a specific controller initiate a group override, the override duration in its local database must
not be zero.
1
On the navigation tree, select the equipment or area that you want to schedule for a group override.
2
Click the
Schedules
page, then
CCN
tab.
3
Enter the number of minutes in
Override Time
.
NOTE
The override setting in the controller must not be set to
0
.
4
Assign a number to
Override group.
To apply a schedule to single equipment or to all equipment in an area
Schedules in i-Vu CCN Pro are typically based on zone occupancy.
1
On the navigation tree, select the equipment you want to schedule.
NOTE
To schedule all equipment in a specified area, select the area you want.
2
Click the
Schedules
page >
Configure
tab.
3
Click
Add
.
4
Select a
Priority
. (
Normal
is low priority;
Holiday
is medium;
Override
is high.)
5
Select a
Type
. See table below.
6
Type a schedule name in the
Description
field.
7
Enter desired values in the fields below
Description
.
8
Change the default time segment (shown as a colored bar) for the schedule by doing one of the
following:
○
Click the segment, then type
Start
and
End
times in the fields above the segment.
○
Click and drag either end of the segment or the entire segment.
Optional: Click
Show Advanced
below the schedule bar to add one or more separate segments to the
schedule.