ABB Network Partner AB
Apparatus control
Version 1.0-00
1MRK 580 150-XEN
Page 6
-
8
2.8 Supervision of
operating apparatus
The control part should check the start conditions (for example, if there is
a select for open when the position is open) for a valid selection, the
movement itself, and correct completion. The corresponding status sig-
nals are given. The operation depends on the interlocking and blocking
signals.
The supervision of the command output is made by the microcontroller on
the output board.
A timer supervises the start of the drive. If the drive does not succeed in
starting within a specified time, the command sequence resets, and an
error indication is generated.
A timer supervises the movement of the drive. The maximum time can be
set between the start and until the new position is reached.
When three phase indications are included, the pole-discordance function
is included.
If blockings and interlocking allow operation, the drive can be operated
when the starting-point is in the intermediate position.
2.9 Synchro-check
Synchro-check conditions can be considered when manually closing a
breaker. The closing command is released via the apparatus control, as for
ordinary operations with the synchro-check function excluded.
A timer supervises the synchro-check function. If there is no synchronism
within a specified time (after a closing command is given), there is a
failed synchronisation.
The REC 561 can use a built-in synchro-check function (also called inter-
nal synchro-check) or use an external synchro-check or synchronising
equipment, which are separate devices outside the REC 561. Two solu-
tions are supported. The explicit closing command can come from the
apparatus control itself (activated by the synchro-check) or from the exter-
nal synchro-check equipment (activated by the apparatus control).
Summary of Contents for REC 561
Page 19: ...ABB Network Partner AB Introduction REC 561 Version 1 0 00 1MRK 580 146 XEN Page 2 14 ...
Page 31: ...ABB Network Partner AB Requirements and basic technical data REC 561 Version 1 0 00 Page 2 26 ...
Page 49: ...ABB Network Partner AB Page IV ...
Page 121: ...ABB Network Partner AB Menu tree Appendix Version 1 0 00 1MRK 580 158 XEN Page 3 72 ...
Page 139: ...ABB Network Partner AB Terminal identification Version 1 0 00 1MRK 580 160 XEN Page 4 4 ...
Page 143: ...ABB Network Partner AB Activation of setting group Version 1 0 00 1MRK 580 162 XEN Page 4 8 ...
Page 175: ...ABB Network Partner AB Configurable logic Version 1 0 00 1MRK 580 161 XEN Page 4 40 ...
Page 385: ...ABB Network Partner AB Apparatus control Version 1 0 00 1MRK 580 150 XEN Page 6 100 ...
Page 495: ...ABB Network Partner AB Interlocking Version 1 0 00 1MRK 580 151 XEN Page 6 210 ...
Page 515: ...ABB Network Partner AB Event function Version 1 0 00 1MRK 580 140 XEN Page 6 230 ...
Page 519: ...ABB Network Partner AB Page IV ...
Page 561: ...ABB Network Partner AB Time synchronisation Version 1 0 00 1MRK 580 135 XEN Page 7 42 ...
Page 569: ...ABB Network Partner AB Internal events Version 1 0 00 1MRK 580 134 XEN Page 7 50 ...
Page 599: ...ABB Network Partner AB Index Version 1 0 01 1MRK 580 175 XEN Page 8 6 ...
Page 634: ......
Page 635: ......
Page 636: ......
Page 637: ......
Page 638: ......
Page 639: ......
Page 640: ......
Page 641: ......
Page 642: ......
Page 643: ......