Compressor switch on/off sequence
Switch on/off sequence of partializations in single compressor installations.
Partialization 1 is always inserted first followed by partialization 2 (unvaried sequence).
•
Partialization 2 is only switched on if partialization 1 is already on.
•
Partialization 1 is switched off only if partialization 2 is already off.
Switch on/off sequence of compressors in twin compressor installations.
The order in which compressors are inserted can be modified using CP02, the compressor switch on sequence:
•
0 = Balancing durations
•
1 = On sequence 1/2; off 2/1
•
2 = On sequence 2/1; off 1/2
•
3 = Limited sequence 1 (only compressor 1 available)
•
4 = Limited sequence 2 (only compressor 2 available)
Run time sequence
•
5 = Run time 1 sequence (based on CP10 Compressor run time for switch on sequence) see table
•
6 = Run time 21 sequence (based on CP10 Compressor run time for switch on sequence) see table
Run time sequence
CP02 = 5
CP02 = 6
Run time 1 sequence
Run time 2 sequence
Real time < CP10:
Switch on sequence:
compressor 1
compressor 2
Switch off sequence:
compressor 2
compressor 1
Real time < CP10:
Switch on sequence:
compressor 2
compressor 1
Switch off sequence:
compressor 1
compressor 2
Real time> CP10:
Switch on sequence:
compressor 2
compressor 1
Switch off sequence:
compressor 1
compressor 2
Real time> CP10:
Switch on sequence:
compressor 1
compressor 2
Switch off sequence:
compressor 2
compressor 1
N.B:
•
When the device is switched on for the first time or in the event of a blackout, the sequence is set in CP02=5);
•
When the machine is OFF or on std-by, the on/off sequences reflect the value assigned to parameter CP02.
Содержание UST500
Страница 1: ...UNIFLAIR Instruction manual UST500 CONTROL BOARD EN...
Страница 97: ...UST500 CONTROL 06MC0074 00B0100 14 04 2010 97...
Страница 98: ...CONTROLLO UST500 98 06MC0074 00B0100 14 04 2010...
Страница 99: ...UST500 CONTROL 06MC0074 00B0100 14 04 2010 99...