GE Multilin
G60 Generator Protection System
5-153
5 SETTINGS
5.5 FLEXLOGIC
5
8.
The logic should always be tested after it is loaded into the relay, in the same fashion as has been used in the past.
Testing can be simplified by placing an "END" operator within the overall set of FlexLogic equations. The equations will
then only be evaluated up to the first "END" operator.
The "On" and "Off" operands can be placed in an equation to establish a known set of conditions for test purposes, and
the "INSERT" and "DELETE" commands can be used to modify equations.
5.5.5 FLEXLOGIC EQUATION EDITOR
PATH: SETTINGS
FLEXLOGIC
FLEXLOGIC EQUATION EDITOR
There are 512 FlexLogic entries available, numbered from 1 to 512, with default END entry settings. If a "Disabled" Element
is selected as a FlexLogic entry, the associated state flag will never be set to ‘1’. The ‘+/–‘ key may be used when editing
FlexLogic equations from the keypad to quickly scan through the major parameter types.
5.5.6 FLEXLOGIC TIMERS
PATH: SETTINGS
FLEXLOGIC
FLEXLOGIC TIMERS
FLEXLOGIC TIMER 1(32)
There are 32 identical FlexLogic timers available. These timers can be used as operators for FlexLogic equations.
•
TIMER 1 TYPE:
This setting is used to select the time measuring unit.
•
TIMER 1 PICKUP DELAY:
Sets the time delay to pickup. If a pickup delay is not required, set this function to "0".
•
TIMER 1 DROPOUT DELAY:
Sets the time delay to dropout. If a dropout delay is not required, set this function to "0".
FLEXLOGIC
EQUATION EDITOR
FLEXLOGIC ENTRY
1:
END
Range: FlexLogic operands
MESSAGE
FLEXLOGIC ENTRY
2:
END
Range: FlexLogic operands
↓
MESSAGE
FLEXLOGIC ENTRY 512:
END
Range: FlexLogic operands
FLEXLOGIC
TIMER 1
TIMER 1
TYPE: millisecond
Range: millisecond, second, minute
MESSAGE
TIMER 1
PICKUP
DELAY: 0
Range: 0 to 60000 in steps of 1
MESSAGE
TIMER 1
DROPOUT
DELAY: 0
Range: 0 to 60000 in steps of 1
Содержание Multilin g60
Страница 10: ...x G60 Generator Protection System GE Multilin TABLE OF CONTENTS INDEX ...
Страница 32: ...1 22 G60 Generator Protection System GE Multilin 1 5 USING THE RELAY 1 GETTING STARTED 1 ...
Страница 130: ...3 68 G60 Generator Protection System GE Multilin 3 4 FIELD AND STATOR GROUND MODULES 3 HARDWARE 3 ...
Страница 160: ...4 30 G60 Generator Protection System GE Multilin 4 3 FACEPLATE INTERFACE 4 HUMAN INTERFACES 4 ...
Страница 486: ...5 326 G60 Generator Protection System GE Multilin 5 10 TESTING 5 SETTINGS 5 ...
Страница 518: ...6 32 G60 Generator Protection System GE Multilin 6 5 PRODUCT INFORMATION 6 ACTUAL VALUES 6 ...
Страница 532: ...7 14 G60 Generator Protection System GE Multilin 7 2 TARGETS 7 COMMANDS AND TARGETS 7 ...
Страница 538: ...8 6 G60 Generator Protection System GE Multilin 8 1 PHASE DISTANCE THROUGH POWER TRANSFORMERS 8 THEORY OF OPERATION 8 ...
Страница 748: ...D 10 G60 Generator Protection System GE Multilin D 1 IEC 60870 5 104 APPENDIX D D ...
Страница 760: ...E 12 G60 Generator Protection System GE Multilin E 2 DNP POINT LISTS APPENDIX E E ...