SiBE37-701_B
Test Operation
Test Operation
156
1. Test Operation
1.1
Installation Process
Below Figure shows the installation process. Install in the order of the steps shown.
3. Selection of Location
4. Inspecting and Handling the Unit
5. Placing the Unit
7. Field Wiring
6. Refrigerant Piping
8. Air Tight Test and Vacuum Drying
9. Pipe Insulation
10. Checking of Device and Installation Conditions
11. Additional Refrigerant Charge and Check Operation
13. Test Run
Operations which require the
power to be turned on.
Содержание REYQ8-48PY1B
Страница 1: ...Service Manual REYQ8 48PY1B R 410A Heat Recovery 50Hz SiBE37 701_B ...
Страница 456: ...Piping Installation Point SiBE37 701_B 445 Appendix ...
Страница 460: ...Example of connection SiBE37 701_B 449 Appendix ...
Страница 476: ...Revision History Date News No Contents 2010 9 10 M 10011 Correction of service manual ...