Chapter 5: Installation
242
Figure 104 :
Rear strap connected to upper AP antenna bracket
5
Attach the entire upper bracket to the antenna using (2) hex bolts, (2) flat washers and (2) lock
washers. Feed the bolt through the lock washer then flat washer, then thread the bolt into the upper
bracket’s threaded receptacle.
Figure 105 :
Assembled upper bracket connected to AP antenna
Note
Use shielded cable for all infrastructure connections associated with APs, SMs, and
CMMs. The environment that these modules operate in often has significant unknown or
varying RF energy. Operator experience consistently indicates that the additional cost
of shielded cables is more than compensated by predictable operation and reduced
costs for troubleshooting and support.
6
Begin assembling the lower bracket by attaching the (2) 7” hex bolts to the bracket using (2)
Содержание PMP 450 Series
Страница 92: ...Chapter 2 System hardware 92 Figure 29 MicroPoP Omni antenna implementation pattern Vertical...
Страница 134: ...Chapter 3 System planning 134 Figure 51 Mast or tower installation...
Страница 135: ...Chapter 3 System planning 135 Figure 52 Wall installation...
Страница 136: ...Chapter 3 System planning 136 Figure 53 Roof installation...
Страница 137: ...Chapter 3 System planning 137 Figure 54 GPS receiver wall installation...
Страница 158: ...Chapter 3 System planning 158 Figure 61 cnMedusa Antenna...
Страница 258: ...Chapter 5 Installation 258 Figure 123 Yagi antenna alignment horizontally Figure 124 Yagi antenna alignment upward tilt...