Chapter 1 Node Start-up and Commissioning
Visual Status During and After Start-up
Release TR3.2.1
Turin Networks
Page 11-11
Visual Status
During and
After Start-up
The GCM power LED indicates the status of start-up and initialization. The GCM
power LED will go through the following sequence:
Flashing red
Power On Self Test (POST) is started
1
.
Solid green
Initialization complete and successful.
1
The POST takes approximately one minute to run and it invokes the LED activity for initialization.
Table 11-8 Power and Active/Standby—GCM Cards
LED
RED
Amber
GREEN
OFF
Flashing
Solid
Flashing
Solid
Flashing
Solid
Power
Initializing;
POST is
started.
Hardware
failure
detected;
replace the
card.
N/A
N/A
Node is in
commissioning
mode
Passed
initialization
and is
operational
No power
Active/
Standby
N/A
N/A
Standby
mode;
synchroniza-
tion with the
Active card
is not
complete.
Card type
does not
match the
provisioned
card type or
the card is
placed in an
invalid slot.
1
Standby mode;
synchroniza-
tion with the
active card is
complete.
Active and
operational
Initializing;
POST is
started.
1
Please refer to Appendix A—“Card Placement Planning and Guidelines,” page 12-1 for valid card placement guidelines.
Important:
The solid green Active/Standby LED indicates the active
GCM card. Use the CLI to commission and configure the active GCM.