Traverse Installation and Commissioning Guide, Section 8: Network Interface Cabling Procedures
Ethernet Protection Cabling at the Electrical Connector Module
Page 8-42
Turin Networks
Release TR3.2.1
8
Tie-wrap cables to the cable management bar(s) following local
procedures.
Figure 8-21 Traverse Shelf with Cable Management Bar(s)
9
Route the cables to the intermediate patch panel located in the same or
adjacent rack per local procedures.
10
Cut the cables to the correct length using cable cutters.
11
Important:
The Turin Telco 50 cable assembly is shielded. Connect a
ground wire to the shielding. Connect the ground wire to the equipment
rack following local procedures.
12
Use a wire wrap tool to terminate the cables at the patch panel or terminate
cable/pairs onto RJ-45 connectors for termination at the patch panel.
Refer to the following tables for detailed connector pinouts and color code
information.
Section 2—
Network Interface Specifications
(Electrical) Interface Cabling Specifications”:
•
•
Table 8-15 Protected GbE TX and 10/100BaseTX Cabling at the ECM (continued)
Step
Procedure
Cable
management
bars
Cables to the
right or left
side