Traverse Installation and Commissioning Guide, Section 10: Power Installation and Cabling Procedures
Connect Battery Supply Cables to the PDAP
Page 10-24
Turin Networks
Release TR3.2.1
Table 10-7 Connect Battery Supply Cables to the PDAP
Step
Procedure
1
Run battery “A” and “B” supply cables from the BDFB across the
horizontal cable rack and down the rack rails to the PDAP following local
procedures.
2
Remove the protective cover from the back of the PDAP. Refer to
Section 6—
Precautions and Common Procedures
Chapter 2—“Removing and Replacing Back Covers,”
, page 6-13 for detailed instructions.
3
Bring the cables to the battery “A” and “B” supply PDAP-4S or
PDAP-15A terminal studs or PDAP-2S bus bars.
Figure 10-12 PDAP-4S Battery Supply Terminal Lugs
Figure 10-13 PDAP-15A Battery Supply Terminal Lugs
4
Cut the battery supply cables to the correct length.
5
Use a crimping tool to attach double-hole copper barrel cable lugs to the
ends of the battery supply cables for connection to the PDAP.
6
Remove the nuts and lock washers from the PDAP battery “A” and “B”
NEG VDC input terminal lugs.
7
Place the double-hole copper barrel cable lug on the battery “A” NEG
VDC input terminal lugs. Replace the lock washers and tighten nuts.
Battery “B” Supply Terminals
Battery “A” Supply Terminals
Battery “A” Supply
Terminals
Battery “B” Supply
Terminals