Release TR3.2.1
Turin Networks
Page 11-1
SECTION 11NODE START-UP AND COMMISSIONING PROCEDURES
Chapter 1
Node Start-up and Commissioning
Introduction
The Traverse node is ready for power-up after all the hardware is installed: shelf, fan
tray, and air ramp, cabling (network, alarm, timing, Ethernet, power), and polarity and
voltage testing are complete. This chapter provides instructions to start-up and
commission a Traverse shelf:
•
•
•
Required Node Commissioning Parameters
•
Conditional Node Commissioning Parameters
•
•
Visual Status During and After Start-up
•
Power and Active/Standby LED Indicators
The instructions may be too detailed if you are experienced in central office
installations. In this case, scan the topic labels in the left margin for tasks to review or
refer to Appendix B—“Installation and Commissioning Checklists,”
Before You
Begin
Review this information before you begin.
Table 11-1 Node Start-up Requirements
Requirement
Reference
Read through the entire chapter and
gather together reference material
first.
Chapter 1—“Node Start-up and Commissioning”
All hardware is installed.
Hardware Installation Procedures
Chapter 1—“Traverse System Rack Installation Overview,”
page 7-1