Release TR3.2.1
Turin Networks
Page 1-1
SECTION 1INSTALLATION OVERVIEW
Chapter 1
Installation and Commissioning Overview
Introduction
This chapter includes the following topics:
•
•
•
Traverse Shelf Interface Specifications
Traverse
Installation
Process
Use these steps as a guideline to installing and commissioning a Traverse system
Important:
Do not install Traverse cards (modules) until all installation
and cabling procedures are complete.
Table 1-1 Installation Process and References
Step
Procedure
Reference
1
Read the precautions before
attempting to install the shelf.
Precautions and Common Procedures
Chapter 1—“Precautions,” page 6-1
2
Familiarize yourself with common
procedures such as inserting and
removing cards and back cover.
Precautions and Common Procedures
3
Install the hardware, e.g., the
optional power distribution and
alarm panel (PDAP) and the
Traverse shelf.
Hardware Installation Procedures
Chapter 1—“Traverse System Rack Installation
Overview,” page 7-1
Power Installation and Cabling
, Chapter 2—“Power System Hardware
4
Install network cabling.
Network Interface Cabling Procedures
5
Install alarm cabling.
Alarm, Timing, and Management Cabling
, Chapter 1—“Alarm Interface Cabling,”
6
Install timing cabling.
Alarm, Timing, and Management Cabling