Economizer Heat Exchanger installation
Install the heat exchanger by performing the following steps:
1. Bolt the economizer heat exchanger to the mounting bracket in the condenser section.
2. Clean the two liquid and two suction lines for soldering.
3. Solder the liquid and suction lines to the economizer heat exchanger.
4. Pressurize the low side and check for leaks (see “Refrigerant Leak Test Procedure” in this chapter).
5. If no leaks are found, recover the leak test gas (see “Refrigerant Leak Test Procedure” in this chapter).
6. Evacuate the low side (see “Evacuation and Cleanup of the Refrigeration System” in this chapter).
7. Recharge the unit with R-404A (see “Charging the System with Refrigerant” in this chapter).
8. Perform a controller pretrip test to verify system operation.
NOTE: Thermo King strongly recommends that dry nitrogen be used to purge the system during any
solder operations (see “Using Pressurized Nitrogen” in this chapter).
Summary of Contents for 098203
Page 2: ......
Page 3: ...MAGNUM TK 60275 4 MM Rev 3 08 15 Copyright 2012 Ingersoll Rand EMEIA Printed in Ireland...
Page 193: ...Refrigeration Maintenance 191 Figure 163 Filter Drier...
Page 200: ...Refrigeration Maintenance 198 Figure 169 Receiver Tank Figure 170 Water Cooled Condenser Tank...
Page 257: ...255 Schematic Diagram RELEASED 19 Sep 2013...
Page 258: ...256 Wiring Diagram Page 1 of 2 RELEASED 19 Sep 2013...
Page 259: ...257 Wiring Diagram Page 2 of 2 RELEASED 19 Sep 2013...
Page 263: ......