![Thermo King 098203 Maintenance Manual Download Page 181](http://html1.mh-extra.com/html/thermo-king/098203/098203_maintenance-manual_1104405181.webp)
Refrigeration Maintenance
179
Purge High Side to Low Side
1. Attach gauge manifold set (see “Gauge Manifold Set Attachment and Purging” for proper procedure
for connecting to compressor).
2. Close both hand valves on the gauge manifold (front seated).
3. Connect charging hose to a source of nitrogen. Adjust pressure regulator to the proper pressure for the
required procedure.
4. Purge system high side to low side.
Maximum Gas Pressures
The following procedures should utilize the following
maximum
gas pressure:
•
Leak Testing: 1034 to 1200 kPa, 10.34 to 12.00 bar, 150-174 psig,
•
Purging/Dehydration: 69 to 138 kPa, 0.69 to 1.38 bar, 10-20 psig,
•
Soldering: 35 kPa, 0.35 bar, 5 psig.
Summary of Contents for 098203
Page 2: ......
Page 3: ...MAGNUM TK 60275 4 MM Rev 3 08 15 Copyright 2012 Ingersoll Rand EMEIA Printed in Ireland...
Page 193: ...Refrigeration Maintenance 191 Figure 163 Filter Drier...
Page 200: ...Refrigeration Maintenance 198 Figure 169 Receiver Tank Figure 170 Water Cooled Condenser Tank...
Page 257: ...255 Schematic Diagram RELEASED 19 Sep 2013...
Page 258: ...256 Wiring Diagram Page 1 of 2 RELEASED 19 Sep 2013...
Page 259: ...257 Wiring Diagram Page 2 of 2 RELEASED 19 Sep 2013...
Page 263: ......