Make sure that the unit is not physically damaged, and that the paint-work is clean
without dents or scratches.
The physical handling of the unit during the installation may have caused some
minor scratches to the paint-work. This can be accepted. However, if rough
handling has caused serious damage to the unit, this must be recorded with a written
statement and necessary photos, so that corrective actions can be made.
4
Make sure that the unit is firmly connected to vessel ground.
a
Make sure that the unit is securely connected to the vessel ground with an
earthing strap. The strap must be in addition to any incidental electrical contact
made by the mounting lugs on the unit.
b
Use a standard multimeter to check that the resistance between the unit and the
ship's ground is approximately 0 (zero) Ω.
5
Make sure that cable installation has been completed.
a
Make sure that all cables leading to and from the unit have been properly
mounted and secured.
b
Make sure that enough slack has been provided on each cable to allow for
maintenance and replacement.
6
Make sure that the unit has been identified with the relevant product label(s), and
that one label includes the part and serial numbers.
Result
Requirements
Results
The Operating Panel is correctly installed with easy access for maintenance
and replacement of parts.
The Operating Panel is free from scratches, dents or other physical damage.
Free access to all the connectors on the Operating Panel are provided.
All cables are properly mounted with enough slack.
The Operating Panel is properly grounded.
Date and signature:
Visual inspection of the Transceiver Unit
A visual inspection of the Transceiver Unit is required to verify that the unit has not been
physically damaged during the installation.
Prerequisites
The SC90 is installed as specified in this manual. The SC90 is turned off. You need
the following equipment:
• Multimeter
Simrad SC90 Installation Manual
Summary of Contents for SC90
Page 2: ......
Page 16: ...14 419050 B Simrad SC90 ...
Page 219: ...419050 B 217 Øverland UPC 3005 Dimensions Cable layout and interconnections ...
Page 223: ...419050 B 221 Øverland UPC 5000P Dimensions Cable layout and interconnections ...
Page 438: ...436 419050 B 427177 Transducer dock dimensions page 494 Simrad SC90 Installation Manual ...
Page 441: ...419050 B 439 Drawing file ...
Page 442: ...440 419050 B Simrad SC90 Installation Manual ...
Page 445: ...419050 B 443 Drawing file ...
Page 452: ...450 419050 B Simrad SC90 Installation Manual ...
Page 455: ...419050 B 453 Drawing file ...
Page 458: ...456 419050 B Simrad SC90 Installation Manual ...
Page 463: ...419050 B 461 Drawing file ...
Page 468: ...466 419050 B Simrad SC90 Installation Manual ...
Page 469: ...419050 B 467 Related topics Installing the optional gate valve DN350 page 84 Drawing file ...
Page 471: ...419050 B 469 Drawing file ...
Page 473: ...419050 B 471 214043 Gate valve installation DN350 Drawing file ...
Page 475: ...419050 B 473 422915 Gate valve installation DN350 Drawing file ...
Page 477: ...419050 B 475 083045 Gate valve installation DN500 Drawing file ...
Page 479: ...419050 B 477 33414 Gate valve dimensions DN350 Drawing file ...
Page 480: ...478 419050 B Simrad SC90 Installation Manual ...
Page 481: ...419050 B 479 Related topics Installing the optional gate valve DN350 page 84 Drawing file ...
Page 482: ...480 419050 B 33473 Gate valve dimensions DN350 Simrad SC90 Installation Manual ...
Page 483: ...419050 B 481 Related topics Installing the optional gate valve DN350 page 84 Drawing file ...
Page 484: ...482 419050 B 33498 Gate valve dimensions DN500 Simrad SC90 Installation Manual ...
Page 485: ...419050 B 483 Drawing file ...
Page 487: ...419050 B 485 37357 Gate valve dimensions DN500 Drawing file ...
Page 488: ...486 419050 B Simrad SC90 Installation Manual ...
Page 489: ...419050 B 487 Related topics Installing the optional gate valve DN500 page 103 Drawing file ...
Page 491: ...419050 B 489 Drawing file ...
Page 494: ...492 419050 B Simrad SC90 Installation Manual ...
Page 495: ...419050 B 493 Related topics Installing the optional gate valve DN350 page 84 Drawing file ...
Page 497: ...419050 B 495 Drawing file ...
Page 542: ... 2018Kongsberg Maritime ISBN xxx ...
Page 543: ......
Page 544: ...Simrad SC90 Fish finding sonar Installation Manual ...