CHAPTER 2 INSTALLATION
– 82 –
NWA-008841-001 Rev.5.0
90ch2001.fm
INSTALLATION OF MAIN EQUIPMENT
Floor Standing Installation
• Check the site for installing the PBX with the work drawing to verify that the
required floor space is ensured and that service entrances and ducts for trunk/
extension cables, power cables and bus cables have been properly worked at
correct positions. See
“Floor Space”
and
“Cable Hole Location”
.
Page 84
,
Page 85
• Mark positions for installation of the PBX main equipment.
For Fixed Equipment, detach the BASE PLATE from the BASE. See
“Floor
Marking for BASE PLATE”
.
Page 86
For Stationary Equipment, see
“Floor Marking for BASE TRAY”
.
Page 86
NOTE:
Measure the level of the floor surface before installing the PBX main
equipment.
• Check the level of the floor. If necessary, adjust the level by inserting spacers
beneath the equipment.
• First open necessary number of preliminary prepared holes using the drill bit
for small-diameter holes, then use the finishing drill bit for finishing drill holes.
See
“Drilling”
.
Page 87
• Detach the front cover of each Module. See
“Detaching FRONT COVER”
.
Page 88
Continued on next page
Start
Checkup
before installation
Marking
Leveling
Detaching Front Cover
Drilling
A
INSTALLATION OF MAIN EQUIPMENT